2313 W 67TH ST 90043

Certificate Information: 2313 W 67TH ST 90043

Application / Permit
21010-10000-02554
Plan Check / Job No.
B21LA09730
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Existing garage to be converted into a new ADU. Reframe new roof.
Permit Issued
Issued on 12/3/2021
Issuing Office
Current Status
CofO Issued on 2/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2021 APPLICANT
Assigned to Plan Check Engineer 6/11/2021 JOE VO
Corrections Issued 6/11/2021 JOE VO
Applicant returned to address corrections 6/25/2021 JOE VO
Plan Check Approved 7/29/2021 JOE VO
Issued 12/3/2021 APPLICANT
CofO in Progress 8/13/2022 ENRIQUE MIRELES
CofO in Progress 8/13/2022 ENRIQUE MIRELES
Permit Finaled 2/19/2023 DEROLD HAUFF
Permit Finaled 2/19/2023 DEROLD HAUFF
CofO Issued 2/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 6/25/2021 RENZ SORIANO
Sewer availability Cleared 6/25/2021 RENZ SORIANO
Address approval Cleared 7/12/2021 RENZ SORIANO

Contact Information

Contractor Recendez Construction; Lic. No.: 1056558-B 14626 BEHRENS AVE      NORWALK, CA 90650

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/10/2021 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 12/10/2021 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/14/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 12/17/2021 Corrections Issued FREDDIE RIVERA
Deputy Drilled-In Anchors 12/22/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 12/22/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 1/27/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 1/27/2022 Partial Approval FREDDIE RIVERA
Green Building Rough 1/27/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 1/27/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 1/27/2022 Approved FREDDIE RIVERA
Insulation 2/7/2022 Approved FREDDIE RIVERA
Drywall Nailing 2/11/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 3/24/2022 Approved ENRIQUE MIRELES
Shower Pan 3/24/2022 Approved ENRIQUE MIRELES
Gas Test 7/7/2022 Approved ENRIQUE MIRELES
Sewer 7/11/2022 Approved ENRIQUE MIRELES
Final 7/19/2022 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 7/19/2022 Approved ENRIQUE MIRELES
Smoke Detectors 7/19/2022 Approved ENRIQUE MIRELES
Final 7/27/2022 Conditional Approval HORACE FULTZ
Final 8/15/2022 OK to Issue CofO ENRIQUE MIRELES