18062 W OXNARD ST 91316
Certificate Information: 18062 W OXNARD ST 91316
- Application / Permit
- 21010-10000-02552
- Plan Check / Job No.
- B21LA09727
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ONE STORY ADU.
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | JOE VO |
| Corrections Issued | 7/10/2021 | JOE VO |
| Quality Review Completed | 7/21/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 4/9/2022 | JOE VO |
| Plan Check Approved | 6/6/2022 | JOE VO |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 12/12/2023 | JON MCHUGH |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
| CofO Issued | 4/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 2/16/2022 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/23/2022 | CARLOS AGUILERA |
| Address approval | Cleared | 4/5/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/25/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 5/23/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 5/23/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Markarian,, Mardiros; Lic. No.: NA53434 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/2/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 8/2/2022 | Approved | SEAN HAUPT |
| Special/Order Compliance | 8/2/2022 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 8/9/2022 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 8/9/2022 | Partial Approval | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 8/15/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 8/15/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 9/2/2022 | Not Ready for Inspection | SEAN HAUPT |
| Underground Mechanical | 9/2/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/22/2022 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 9/22/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 9/22/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 9/22/2022 | Approved | SEAN HAUPT |
| Shower Pan | 9/22/2022 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 9/27/2022 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/30/2022 | Partial Approval | SEAN HAUPT |
| Green Building Rough | 9/30/2022 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 9/30/2022 | Approved | SEAN HAUPT |
| Insulation | 10/5/2022 | No Access for Inspection | MORRIS JACKSON |
| Insulation | 10/6/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 10/12/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/12/2022 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 12/8/2022 | Approved | SEAN HAUPT |
| Final | 12/8/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 12/8/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 12/8/2022 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 12/8/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 6/16/2023 | Approved | SEAN WIRCH |
| Final | 6/16/2023 | Partial Approval | SEAN WIRCH |
| HVAC-Final | 6/16/2023 | Approved | SEAN WIRCH |
| PLUMBING-Final | 6/16/2023 | Approved | SEAN WIRCH |
| Service/Power Release | 6/16/2023 | Approved | SEAN WIRCH |
| Verify Rec and Parks Fee Memo | 6/16/2023 | Approved | SEAN WIRCH |
| Final | 12/12/2023 | OK to Issue CofO | JON MCHUGH |
| Service/Power Release | 12/13/2023 | Approved | SEAN WIRCH |