1855 W 94TH ST 90047
Certificate Information: 1855 W 94TH ST 90047
- Application / Permit
- 21010-10000-02549
- Plan Check / Job No.
- B21LA09724
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) GARAGE TO ADU PER GCS 65852.2 AND 65852.22
- Permit Issued
- Issued on 7/26/2022
- Issuing Office
- Current Status
- CofO Issued on 8/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2021 | HERNAN ARREOLA |
| Corrections Issued | 8/16/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/14/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/2/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/31/2022 | HERNAN ARREOLA |
| Plan Check Approved | 4/11/2022 | HERNAN ARREOLA |
| Issued | 7/26/2022 | APPLICANT |
| CofO in Progress | 6/27/2025 | WAYNE REGESTER |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
| CofO Issued | 8/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 2/9/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | ABEL CASILLAS |
| Construction within easement | Cleared | 3/21/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/16/2024 | Conditional Approval | JOSE MACIAS |
| Footing/Foundation/Slab | 2/28/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 3/4/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 3/19/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 3/19/2024 | Not Ready for Inspection | JOSE MACIAS |
| Footing/Foundation/Slab | 6/20/2024 | Not Ready for Inspection | JOSE MACIAS |
| Deputy Reinf. Concrete | 7/9/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 7/10/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 8/14/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 8/14/2024 | Approved | JOSE MACIAS |
| Deputy Drilled-In Anchors | 8/19/2024 | Conditional Approval | JOSE MACIAS |
| Footing/Foundation/Slab | 8/21/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Drilled-In Anchors | 8/26/2024 | Conditional Approval | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 8/28/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 10/1/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/29/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 10/29/2024 | Conditional Approval | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/8/2024 | Conditional Approval | AMIR NAZARIAN |
| ELECTRICAL-Rough | 12/2/2024 | Conditional Approval | AMIR NAZARIAN |
| HVAC-Rough | 12/2/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 12/6/2024 | Partial Inspection | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2024 | Approved | JOSE MACIAS |
| METHANE-Rough | 12/20/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 12/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Shower Pan | 12/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Interior/Exterior Lathing | 12/31/2024 | Not Ready for Inspection | BARRY HACHE |
| Shower Pan | 12/31/2024 | Not Ready for Inspection | BARRY HACHE |
| Interior/Exterior Lathing | 1/3/2025 | Corrections Issued | AMIR NAZARIAN |
| Shower Pan | 1/3/2025 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 1/7/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 1/14/2025 | Conditional Approval | JOHN QUINTANILLA |
| Insulation | 1/14/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 1/21/2025 | Approved | BARRY HACHE |
| Green Building Rough | 1/21/2025 | Approved | BARRY HACHE |
| Service/Power Release | 4/3/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 5/13/2025 | Approved | WAYNE REGESTER |
| Final | 5/13/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 5/13/2025 | Corrections Issued | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Smoke Detectors | 5/13/2025 | Approved | WAYNE REGESTER |
| Final | 5/16/2025 | Partial Approval | WAYNE REGESTER |
| Green Building Final | 5/16/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | WAYNE REGESTER |
| Final | 6/26/2025 | OK to Issue CofO | WAYNE REGESTER |