Certificate Information: 1855 W 94TH ST 90047

Application / Permit
21010-10000-02549
Plan Check / Job No.
B21LA09724
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) GARAGE TO ADU PER GCS 65852.2 AND 65852.22
Permit Issued
Issued on 7/26/2022
Issuing Office
Current Status
CofO Issued on 8/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/16/2021 HERNAN ARREOLA
Corrections Issued 8/16/2021 HERNAN ARREOLA
Applicant returned to address corrections 12/14/2021 HERNAN ARREOLA
Applicant returned to address corrections 2/2/2022 HERNAN ARREOLA
Applicant returned to address corrections 3/31/2022 HERNAN ARREOLA
Plan Check Approved 4/11/2022 HERNAN ARREOLA
Issued 7/26/2022 APPLICANT
CofO in Progress 6/27/2025 WAYNE REGESTER
Permit Finaled 8/24/2025 DEROLD HAUFF
Permit Finaled 8/24/2025 DEROLD HAUFF
CofO Issued 8/24/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/9/2022 ABEL CASILLAS
Sewer availability Cleared 2/9/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 2/10/2022 ABEL CASILLAS
Construction within easement Cleared 3/21/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/16/2024 Conditional Approval JOSE MACIAS
Footing/Foundation/Slab 2/28/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 3/4/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 3/19/2024 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 3/19/2024 Not Ready for Inspection JOSE MACIAS
Footing/Foundation/Slab 6/20/2024 Not Ready for Inspection JOSE MACIAS
Deputy Reinf. Concrete 7/9/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 7/10/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 8/14/2024 Approved JOSE MACIAS
Underground Mechanical 8/14/2024 Approved JOSE MACIAS
Deputy Drilled-In Anchors 8/19/2024 Conditional Approval JOSE MACIAS
Footing/Foundation/Slab 8/21/2024 Corrections Issued JOSE MACIAS
Deputy Drilled-In Anchors 8/26/2024 Conditional Approval JOSE MACIAS
Excavation/Setback/Form/Re-Bar 8/28/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 8/28/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 10/1/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 10/29/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 10/29/2024 Conditional Approval AMIR NAZARIAN
ELECTRICAL-Rough 11/8/2024 Conditional Approval AMIR NAZARIAN
ELECTRICAL-Rough 12/2/2024 Conditional Approval AMIR NAZARIAN
HVAC-Rough 12/2/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 12/6/2024 Partial Inspection ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Approved JOSE MACIAS
METHANE-Rough 12/20/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 12/27/2024 Corrections Issued AMIR NAZARIAN
Shower Pan 12/27/2024 Corrections Issued AMIR NAZARIAN
Interior/Exterior Lathing 12/31/2024 Not Ready for Inspection BARRY HACHE
Shower Pan 12/31/2024 Not Ready for Inspection BARRY HACHE
Interior/Exterior Lathing 1/3/2025 Corrections Issued AMIR NAZARIAN
Shower Pan 1/3/2025 Approved AMIR NAZARIAN
Interior/Exterior Lathing 1/7/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 1/14/2025 Conditional Approval JOHN QUINTANILLA
Insulation 1/14/2025 Approved JOHN QUINTANILLA
Drywall Nailing 1/21/2025 Approved BARRY HACHE
Green Building Rough 1/21/2025 Approved BARRY HACHE
Service/Power Release 4/3/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 5/13/2025 Approved WAYNE REGESTER
Final 5/13/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 5/13/2025 Corrections Issued WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Not Ready WAYNE REGESTER
Smoke Detectors 5/13/2025 Approved WAYNE REGESTER
Final 5/16/2025 Partial Approval WAYNE REGESTER
Green Building Final 5/16/2025 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Approved WAYNE REGESTER
Final 6/26/2025 OK to Issue CofO WAYNE REGESTER