3113 S CARTER AVE 90292
Certificate Information: 3113 S CARTER AVE 90292
- Application / Permit
- 21010-10000-02521
- Plan Check / Job No.
- B21LA09597
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW DETACHED 2-STORY ADU PER LAMC 12.22 A.33 (c)-(d) WITH ROOF DECK. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- Metro
- Current Status
- Issued on 4/17/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/15/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 6/22/2021 | JASON HEALEY |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| Applicant returned to address corrections | 3/1/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 3/1/2023 | MAHNAZ NOURHASHEMI |
| Issued | 4/17/2023 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/3/2021 | GILBERT URREA |
| Specific Plan | Cleared | 10/12/2021 | VALERIA CEJA |
| Specific Plan | Cleared | 10/12/2021 | VALERIA CEJA |
| Address approval | Cleared | 10/13/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 10/13/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 10/13/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 10/13/2021 | HISASHI KOBAYAKAWA |
| Coastal Zone | Cleared | 2/9/2022 | NOAH MCCOY |
| Specific Plan | Cleared | 2/9/2022 | NOAH MCCOY |
| Specific Plan | Cleared | 2/9/2022 | NOAH MCCOY |
| ZA Case | Cleared | 2/9/2022 | NOAH MCCOY |
| Low Impact Development | Cleared | 2/17/2023 | ERNEST TSE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 5/12/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/12/2023 | Approved | JESUS RODRIGUEZ |
| METHANE-Barrier | 5/12/2023 | Approved | JESUS RODRIGUEZ |
| METHANE-Subgrade | 5/12/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/19/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/19/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 6/9/2023 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 6/9/2023 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 6/9/2023 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 7/5/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 12/19/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 12/19/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 12/19/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/9/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 6/14/2024 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 6/14/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/14/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 7/3/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/26/2024 | Approved | JESUS PINEDA |
| Underground Mechanical | 8/26/2024 | Partial Approval | JESUS PINEDA |