240-240 1/2 W 84TH ST 90003
Certificate Information: 240-240 1/2 W 84TH ST 90003
- Application / Permit
- 21010-10000-02518
- Plan Check / Job No.
- B21LA09593
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 3-STORY 1173 SF SFD W/ 1656 SF ATTACHED ADU. BOTH SFD AND ADU TO BE EQUIPPED WITH NFPA -13D FIRE SPRINKLERS. 1 OF 2
- Permit Issued
- Issued on 2/14/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 6/15/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 6/23/2021 | WING SUEN |
| Building Plans Picked Up | 7/14/2021 | APPLICANT |
| Applicant returned to address corrections | 10/10/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 12/27/2023 | CRYSTEL MAALOUF |
| Issued | 2/14/2024 | APPLICANT |
| CofO in Progress | 12/17/2024 | MICHAEL LEWIS |
| CofO Issued | 12/18/2024 | DEROLD HAUFF |
| Permit Finaled | 12/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2023 | CHRISTINA BRACO |
| Frnt yard landscape/Water mgmt | Cleared | 10/25/2023 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 11/3/2023 | CHRISTINA BRACO |
| Hydrant and Access approval | Cleared | 11/20/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 12/11/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/12/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/12/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/12/2024 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 3/12/2024 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/21/2024 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 6/28/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 7/8/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 7/8/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 7/10/2024 | Partial Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 7/10/2024 | Conditional Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/19/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/31/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 7/31/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 7/31/2024 | Approved | MICHAEL LEWIS |
| MERV13>=Rough | 7/31/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 7/31/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 8/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 8/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/6/2024 | Approved | MICHAEL LEWIS |
| Insulation | 8/6/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 8/13/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Drywall Nailing | 8/15/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/15/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 12/6/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 12/6/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 12/6/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 12/10/2024 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/10/2024 | Approved | MICHAEL LEWIS |
| Green Building Final | 12/10/2024 | Approved | MICHAEL LEWIS |
| MERV13>=Final | 12/10/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Not Required | MICHAEL LEWIS |
| Service/Power Release | 12/10/2024 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 12/10/2024 | Approved | MICHAEL LEWIS |
| Final | 12/16/2024 | OK to Issue CofO | MICHAEL LEWIS |