770 N NAPOLI DR 90272
Certificate Information: 770 N NAPOLI DR 90272
- Application / Permit
- 21010-10000-02495
- Plan Check / Job No.
- B21LA09472
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW DETACHED, UNENCLOSED, COVERED POOL PAVILION STRUCTURE, 390 SQUARE FEET
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | VARAND SARKISIAN |
| Corrections Issued | 7/8/2021 | VARAND SARKISIAN |
| Quality Review Completed | 7/13/2021 | HANS SANTIAGO |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| Plan Check Approved | 11/15/2021 | VARAND SARKISIAN |
| Issued | 12/15/2021 | APPLICANT |
| CofO in Progress | 1/5/2024 | ARAM AVEDISIAN |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
| CofO Issued | 1/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/14/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 7/19/2021 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 9/1/2021 | MATTHEW CRAIG |
Contact Information
| Architect | Ward,, Charles L; Lic. No.: C32266 | 418 S JUNE ST LOS ANGELES, CA 90020 |
| Contractor | Aragon Fine Homes Inc; Lic. No.: 992249-B | 766 NORTH WORKMAN STREET SAN FERNANDO, CA 91340 |
| Engineer | Roth,, Jennifer Nicole; Lic. No.: C84889 | 110 THE VILLAGE UNIT 504 REDONDO BEACH, CA 90277 |
| Geologist | Daugherty,, Daniel Thomas; Lic. No.: EG2569 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/19/2022 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/23/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 5/25/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 6/24/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/13/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/29/2022 | Partial Approval | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 8/29/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/13/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/13/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/13/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/15/2022 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/11/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 4/11/2023 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/11/2023 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 4/11/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 5/8/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 1/5/2024 | OK to Issue CofO | ARAM AVEDISIAN |