3136 S PURDUE AVE 90066
Certificate Information: 3136 S PURDUE AVE 90066
- Application / Permit
- 21010-10000-02445
- Plan Check / Job No.
- B21LA09315
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) & (d). HUD/HCD APPROVED STRUCTURE
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Current Status
- CofO Issued on 2/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | LAMAR DAVIS |
| Corrections Issued | 6/14/2021 | LAMAR DAVIS |
| Quality Review Completed | 6/17/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/14/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 8/11/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 9/3/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 8/3/2022 | LAMAR DAVIS |
| Plan Check Approved | 8/12/2022 | LAMAR DAVIS |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 2/14/2024 | JESUS PINEDA |
| Permit Finaled | 2/20/2024 | DANIEL ORRANTE |
| CofO Issued | 2/20/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/20/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | DINAH GARIN |
| Sewer availability | Cleared | 7/26/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 7/27/2021 | TIMOTHY POWELL |
| Specific Plan | Cleared | 9/22/2021 | PEDRO AYALA |
| Miscellaneous | Cleared | 12/6/2021 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 12/14/2021 | LONDY ALVARADO |
| Miscellaneous | Cleared | 12/19/2021 | LAMAR DAVIS |
| Roof/Waste drainage to street | Cleared | 12/29/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 1/14/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/14/2022 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 7/26/2022 | AL GAMBLE |
| Hydrant and Access approval | Cleared | 8/29/2022 | FIRE DEPARTMENT |
Contact Information
| Contractor | Natomas Labs Inc; Lic. No.: 1077688-B | , |
| Contractor | Villa Technologies Inc; Lic. No.: 1077688-B | , |
| Engineer | Anis,, Mohsen; Lic. No.: C69482 | 2190 WEMBLEY LN CORONA, CA 92881 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/1/2022 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/13/2022 | Partial Approval | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 9/27/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/30/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/4/2022 | Approved | JOHNNY MIRANDA |
| Sewer | 10/24/2022 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 11/7/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 7/11/2023 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/23/2023 | Not Ready for Inspection | JESUS PINEDA |
| Drywall Nailing | 10/23/2023 | Approved | JESUS PINEDA |
| Final | 10/23/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 10/23/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 10/23/2023 | Approved | JESUS PINEDA |
| MERV13>=Final | 10/23/2023 | Approved | JESUS PINEDA |
| MERV13>=Rough | 10/23/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 10/23/2023 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 10/23/2023 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 10/23/2023 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/21/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Final | 11/21/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Service/Power Release | 11/21/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 11/21/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Final | 11/30/2023 | Corrections Issued | JESUS PINEDA |
| Service/Power Release | 11/30/2023 | Partial Inspection | KENNETH NAGLE |
| Final | 2/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Service/Power Release | 2/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 2/14/2024 | OK to Issue CofO | JESUS PINEDA |
| Service/Power Release | 2/14/2024 | Approved | JESUS PINEDA |