5077 N MOUNT HELENA AVE 90041

Certificate Information: 5077 N MOUNT HELENA AVE 90041

Application / Permit
21010-10000-02429
Plan Check / Job No.
B21LA09251
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW STATE APPROVED PREFAB A.D.U 800 S.F MAX. PER GCS65852.2(e)(1)(b) and LAMC 12.22 A .33 (c)(d)and (g). INSPECTOR TO VERIFY THE INSIGNIA OF APPROVAL ISSUED BY HCD ON THE FACTORY-BUILT HOUSING. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 3/9/2022
Issuing Office
Current Status
CofO Issued on 12/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 YOUNG KIM
Corrections Issued 6/9/2021 YOUNG KIM
Quality Review Completed 6/10/2021 SAI KHUM
Building Plans Picked Up 6/16/2021 APPLICANT
Applicant returned to address corrections 6/23/2021 YOUNG KIM
Applicant returned to address corrections 6/24/2021 YOUNG KIM
Applicant returned to address corrections 7/13/2021 YOUNG KIM
Applicant returned to address corrections 11/17/2021 YOUNG KIM
Applicant returned to address corrections 12/22/2021 YOUNG KIM
Applicant returned to address corrections 12/28/2021 YOUNG KIM
Applicant returned to address corrections 1/25/2022 YOUNG KIM
Applicant returned to address corrections 2/24/2022 YOUNG KIM
Plan Check Approved 3/8/2022 YOUNG KIM
Issued 3/9/2022 APPLICANT
CofO in Progress 12/20/2022 HAMIK HARTOUNIAN
CofO Issued 12/28/2022 DEROLD HAUFF
Permit Finaled 12/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 5/25/2021 JASON SHEETS
"D" conditions Cleared 8/3/2021 MINDY NGUYEN
"Q" conditions Cleared 8/3/2021 MINDY NGUYEN
Miscellaneous Cleared 8/3/2021 MINDY NGUYEN
ZA Case Cleared 8/3/2021 MINDY NGUYEN
Specific Plan Cleared 8/24/2021 ADRINEH MELKONIAN
Address approval Cleared 9/28/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/28/2021 RENZ SORIANO
Sewer availability Cleared 9/29/2021 RENZ SORIANO
Specific Plan Cleared 9/29/2021 MOHAMMAD HASAN
Grading Pre-Inspection Cleared 10/2/2021 ROBERT HUGHES
GPI Written Notices Cleared 11/16/2021 SAI KHUM
Roof/Waste drainage to street Cleared 11/19/2021 WALLIE JONG
Hydrant and Access approval Cleared 12/14/2021 MATTHEW CRAIG

Contact Information

Contractor Backyard Estates Llc; Lic. No.: 1076065-B 4245 STONE CIRCLE      LA VERNE, CA 91750
Engineer Anis,, Mohsen Magdy; Lic. No.: C69482 2190 WEMBLEY LN      CORONA, CA 92881

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/13/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 6/1/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 6/7/2022 Approved CRAIG VAUGHAN
Sewer 7/5/2022 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/14/2022 Partial Approval CRAIG VAUGHAN
Gas Test 7/14/2022 Approved CRAIG VAUGHAN
Green Building Rough 7/14/2022 Approved CRAIG VAUGHAN
MERV13>=Rough 7/14/2022 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 7/14/2022 Corrections Issued CRAIG VAUGHAN
Sewer 8/4/2022 Corrections Issued HAMIK HARTOUNIAN
Gas Test 8/11/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Sewer 8/11/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Gas Test 8/17/2022 Approved CRAIG VAUGHAN
Sewer 8/17/2022 Approved CRAIG VAUGHAN
Underground Mechanical 8/17/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 9/8/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 9/8/2022 Corrections Issued SCOTT FINNILA
Final 9/8/2022 Corrections Issued SCOTT FINNILA
Green Building Final 9/8/2022 Corrections Issued SCOTT FINNILA
HVAC-Final 9/8/2022 Corrections Issued SCOTT FINNILA
PLUMBING-Final 9/8/2022 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 9/8/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 9/9/2022 Not Ready for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 10/14/2022 Conditional Approval CRAIG VAUGHAN
Final 10/14/2022 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 10/14/2022 Approved CRAIG VAUGHAN
MERV13>=Final 10/14/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/14/2022 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 10/14/2022 Corrections Issued CRAIG VAUGHAN
Smoke Detectors 10/14/2022 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 10/14/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 12/1/2022 Partial Approval CRAIG VAUGHAN
Final 12/1/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 12/1/2022 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 12/1/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 12/1/2022 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 12/1/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 12/9/2022 Approved CRAIG VAUGHAN
Final 12/9/2022 Partial Inspection CRAIG VAUGHAN
Service/Power Release 12/9/2022 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 12/9/2022 Approved CRAIG VAUGHAN
Final 12/19/2022 OK to Issue CofO HAMIK HARTOUNIAN