439-441 E 118TH ST 90061

Certificate Information: 439-441 E 118TH ST 90061

Application / Permit
21010-10000-02404
Plan Check / Job No.
B21LA09197
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan Backroom NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 JOE VO
Corrections Issued 6/5/2021 JOE VO
Quality Review Completed 6/10/2021 MICHAEL PEREZ
Plan Check Approved 8/11/2021 JOE VO
Issued 8/18/2021 APPLICANT
Building Plans Picked Up 8/30/2021 APPLICANT
CofO in Progress 7/12/2022 ALEJANDRO DE ARTOLA
Permit Finaled 7/23/2022 DEROLD HAUFF
CofO Issued 7/23/2022 DEROLD HAUFF
Permit Finaled 7/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/24/2021 STEVE MELGAR
Permit Cleared 6/24/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/1/2021 STEVE MELGAR
Sewer availability Cleared 7/7/2021 STEVE MELGAR
Low Impact Development Cleared 7/19/2021 MARCO SANCHEZ
Hydrant and Access approval Cleared 7/20/2021 ROBERT DUFF
Roof/Waste drainage to street Cleared 7/27/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/29/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Not Ready for Inspection CRAIG DAVIS
Underground Mechanical 10/18/2021 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/19/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 10/19/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Partial Approval EUGENE CASSIDY
Insulation 10/22/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 1/21/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 1/21/2022 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 1/21/2022 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 1/21/2022 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 1/21/2022 Approved ALIZAH MAYAGOITIA
Insulation 1/24/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/8/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 2/8/2022 Approved JOHN KLARIN
ELECTRICAL-Final 4/18/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 5/17/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/17/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/17/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/17/2022 Approved ALEJANDRO DE ARTOLA
Green Building Final 5/17/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/17/2022 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 5/17/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/17/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/17/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 5/17/2022 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 5/17/2022 Approved ALEJANDRO DE ARTOLA
Service/Power Release 5/18/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/11/2022 Approved ALEJANDRO DE ARTOLA
Final 7/11/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 7/11/2022 Approved ALEJANDRO DE ARTOLA
MERV13>=Final 7/11/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/11/2022 Approved ALEJANDRO DE ARTOLA