439-441 E 118TH ST 90061
Certificate Information: 439-441 E 118TH ST 90061
- Application / Permit
- 21010-10000-02404
- Plan Check / Job No.
- B21LA09197
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan Backroom NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE.
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofO Issued on 7/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | JOE VO |
| Corrections Issued | 6/5/2021 | JOE VO |
| Quality Review Completed | 6/10/2021 | MICHAEL PEREZ |
| Plan Check Approved | 8/11/2021 | JOE VO |
| Issued | 8/18/2021 | APPLICANT |
| Building Plans Picked Up | 8/30/2021 | APPLICANT |
| CofO in Progress | 7/12/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 7/23/2022 | DEROLD HAUFF |
| CofO Issued | 7/23/2022 | DEROLD HAUFF |
| Permit Finaled | 7/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2021 | STEVE MELGAR |
| Permit | Cleared | 6/24/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 7/7/2021 | STEVE MELGAR |
| Low Impact Development | Cleared | 7/19/2021 | MARCO SANCHEZ |
| Hydrant and Access approval | Cleared | 7/20/2021 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 7/27/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/29/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Not Ready for Inspection | CRAIG DAVIS |
| Underground Mechanical | 10/18/2021 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 10/19/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 10/22/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/21/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 1/21/2022 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 1/21/2022 | Approved | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 1/21/2022 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 1/21/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 1/24/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/8/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 2/8/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 4/18/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 5/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 5/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 5/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/18/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/11/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/11/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/11/2022 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 7/11/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/11/2022 | Approved | ALEJANDRO DE ARTOLA |