12512 W RUBENS AVE 90066

Certificate Information: 12512 W RUBENS AVE 90066

Application / Permit
21010-10000-02383
Plan Check / Job No.
B21LA09126
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage to DETACHED Accessory Dwelling Unit. PER STATE LAW
Permit Issued
Issued on 8/4/2021
Issuing Office
Current Status
CofO Issued on 6/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 5/17/2021 JOE VO
Corrections Issued 5/18/2021 CARLOS MONTES
Applicant returned to address corrections 7/13/2021 JOE VO
Plan Check Approved 7/21/2021 JOE VO
Issued 8/4/2021 APPLICANT
CofO in Progress 5/26/2022 JESUS RODRIGUEZ
Permit Finaled 6/1/2022 DANIEL ORRANTE
CofO Issued 6/1/2022 DANIEL ORRANTE
Permit Finaled 6/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/8/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/14/2021 DINAH GARIN
Sewer availability Cleared 6/14/2021 DINAH GARIN
Specific Plan Cleared 6/29/2021 VALERIA CEJA
Miscellaneous Cleared 7/16/2021 RAYMOND MUGAMBWA

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: C24587 21243 VENTURA BLVD #115      WOODLAND HILLS, CA 91364
Architect Di, Zitti, Fernando; Lic. No.: NA24587       ,
Contractor Davda Construction; Lic. No.: 1066309-B 21044 SHERMAN WAY #105      CANOGA PARK, CA 91303

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2021 Not Ready for Inspection DAVID FEILER
Deputy Drilled-In Anchors 11/12/2021 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 11/17/2021 Conditional Approval DAVID FEILER
Sewer 11/17/2021 Approved DAVID FEILER
Underground Mechanical 11/17/2021 Partial Approval DAVID FEILER
Green Building Rough 1/20/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/20/2022 Approved ENRIQUE MIRELES
Wood Frame 2/17/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 2/23/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/23/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 3/3/2022 Approved ENRIQUE MIRELES
Insulation 3/3/2022 Approved ENRIQUE MIRELES
Wood Frame 3/8/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 3/15/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/23/2022 Approved RYAN SALAZAR
Footing/Foundation/Slab 4/12/2022 Approved JESUS RODRIGUEZ
Final 5/13/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 5/13/2022 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/13/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 5/13/2022 Approved JESUS RODRIGUEZ
Final 5/26/2022 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 5/26/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Approved JESUS RODRIGUEZ