2015 W 92ND ST 90047

Certificate Information: 2015 W 92ND ST 90047

Application / Permit
21010-10000-02381
Plan Check / Job No.
B21LA09123
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert existing detached garage to accessory dwelling unit per LAMC 12.22A.33(b)(5)
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Issued on 2/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 5/17/2021 MONICA RAMIREZ
Corrections Issued 5/17/2021 MONICA RAMIREZ
Applicant returned to address corrections 8/30/2021 MONICA RAMIREZ
Plan Check Approved 11/1/2021 MONICA RAMIREZ
Issued 11/10/2021 APPLICANT
CofO in Progress 4/25/2022 HORACE FULTZ
Permit Finaled 2/19/2023 DEROLD HAUFF
CofO Issued 2/19/2023 DEROLD HAUFF
Permit Finaled 2/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/25/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 5/25/2021 CECILIO NAVARRO
Sewer availability Cleared 5/25/2021 CECILIO NAVARRO
Construction near power lines Cleared 10/27/2021 OSCAR CASTRO

Contact Information

Contractor New Construction & Remodeling; Lic. No.: 1041658-B 8932 COLUMBUS AVE APT 1      NORTH HILLS, CA 91343
Engineer Tabar,, Mehrdad; Lic. No.: C37433 14252 CULVER DR A349      IRVINE, CA 92604

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/22/2021 Approved FREDDIE RIVERA
Sewer 12/22/2021 Approved FREDDIE RIVERA
Underground Mechanical 12/22/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 1/27/2022 Approved FREDDIE RIVERA
Green Building Rough 1/27/2022 Approved FREDDIE RIVERA
HVAC-Rough 1/27/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 1/27/2022 Approved FREDDIE RIVERA
Wood Frame 1/27/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Not Ready for Inspection FREDDIE RIVERA
Insulation 2/7/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 2/7/2022 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/9/2022 Approved FREDDIE RIVERA
Drywall Nailing 2/11/2022 Approved FREDDIE RIVERA
Shower Pan 2/24/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/11/2022 SGSOV Not Ready ENRIQUE MIRELES
BUILDING-Rough-Frame 4/15/2022 Corrections Issued HORACE FULTZ
ELECTRICAL-Final 4/15/2022 Approved HORACE FULTZ
Final 4/15/2022 Not Ready for Inspection HORACE FULTZ
Green Building Final 4/15/2022 Approved HORACE FULTZ
HVAC-Final 4/15/2022 Approved HORACE FULTZ
METHANE-Final 4/15/2022 Corrections Issued HORACE FULTZ
METHANE-Rough 4/15/2022 Corrections Issued HORACE FULTZ
PLUMBING-Final 4/15/2022 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Approved HORACE FULTZ
Smoke Detectors 4/15/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 4/22/2022 Approved HORACE FULTZ
Final 4/22/2022 OK to Issue CofO HORACE FULTZ
METHANE-Final 4/22/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 4/25/2022 Approved HORACE FULTZ
METHANE-Final 4/25/2022 Approved HORACE FULTZ