127-129 E 112TH ST 90061
Certificate Information: 127-129 E 112TH ST 90061
- Application / Permit
- 21010-10000-02375
- Plan Check / Job No.
- B21LA09096
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE. NFPA-13 D REQUIRE.
- Permit Issued
- Issued on 9/3/2021
- Issuing Office
- Current Status
- CofO Issued on 4/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2021 | ZAW HAN |
| Corrections Issued | 6/8/2021 | ZAW HAN |
| Quality Review Completed | 6/15/2021 | WING SUEN |
| Applicant returned to address corrections | 8/24/2021 | ZAW HAN |
| Plan Check Approved | 8/25/2021 | ZAW HAN |
| Issued | 9/3/2021 | APPLICANT |
| Building Plans Picked Up | 9/8/2021 | APPLICANT |
| CofO in Progress | 3/22/2022 | JOHN KLARIN |
| Permit Finaled | 4/1/2022 | DEROLD HAUFF |
| CofO Issued | 4/1/2022 | DEROLD HAUFF |
| Permit Finaled | 4/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 6/15/2021 | TERRI OSBORNE |
| Address approval | Cleared | 7/13/2021 | CELINA MORENO |
| Address approval | Cleared | 7/13/2021 | CELINA MORENO |
| Permit | Cleared | 7/13/2021 | CELINA MORENO |
| Trees in Parkway | Cleared | 7/15/2021 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | CELINA MORENO |
| Sewer availability | Cleared | 7/20/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 7/26/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 8/5/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/10/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/22/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2021 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 11/3/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 11/4/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2021 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 12/23/2021 | Not Ready for Inspection | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 12/23/2021 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/3/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 1/3/2022 | Approved | EUGENE CASSIDY |
| Insulation | 1/3/2022 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/3/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 1/12/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 1/12/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/2/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/16/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 3/16/2022 | Approved | JOHN KLARIN |
| Final | 3/16/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 3/16/2022 | Approved | JOHN KLARIN |
| HVAC-Final | 3/16/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 3/16/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 3/16/2022 | Approved | JOHN KLARIN |
| Smoke Detectors | 3/16/2022 | Approved | JOHN KLARIN |
| Special/Order Compliance | 3/17/2022 | Approved | JOHN KLARIN |
| Final | 3/22/2022 | OK to Issue CofO | JOHN KLARIN |