847-849 E 81ST ST 90001

Certificate Information: 847-849 E 81ST ST 90001

Application / Permit
21010-10000-02354
Plan Check / Job No.
B21LA09004
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW DUPLEX WITH ATTACHED GARAGE.
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 KEVIN MORALES
Corrections Issued 6/25/2021 KEVIN MORALES
Quality Review Completed 6/30/2021 EUGENE BARBEAU
Building Plans Picked Up 7/6/2021 APPLICANT
Plan Check Approved 8/25/2021 KEVIN MORALES
Issued 8/31/2021 APPLICANT
CofO in Progress 3/5/2022 ALEJANDRO DE ARTOLA
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 7/15/2021 JOHN KIM
Address approval Cleared 7/16/2021 WALLIE JONG
Permit Cleared 7/16/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/20/2021 WALLIE JONG
Sewer availability Cleared 7/20/2021 WALLIE JONG
Hydrant and Access approval Cleared 7/21/2021 MATTHEW CRAIG
Low Impact Development Cleared 8/6/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 8/18/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/17/2021 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 9/20/2021 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 10/20/2021 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 10/20/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
Sewer 10/20/2021 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 10/20/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 10/26/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
Insulation 10/26/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 10/28/2021 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/8/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/8/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 12/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/16/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 12/16/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/16/2021 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 12/16/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/20/2021 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 12/20/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/21/2021 Not Ready for Inspection ADAM ESCOTO
Green Building Rough 12/21/2021 Not Ready for Inspection ADAM ESCOTO
Wood Frame 12/21/2021 Not Ready for Inspection ADAM ESCOTO
BUILDING-Rough-Frame 12/23/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 12/23/2021 Approved ALEJANDRO DE ARTOLA
Insulation 12/23/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/28/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 12/28/2021 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/28/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/14/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 3/1/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 3/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/1/2022 Approved ALEJANDRO DE ARTOLA
Gas Test 3/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 3/1/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 3/1/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 3/1/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 3/1/2022 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 3/1/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/2/2022 Approved ALEJANDRO DE ARTOLA
Final 3/2/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 3/2/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 3/2/2022 Approved ALEJANDRO DE ARTOLA
Final 3/4/2022 OK to Issue CofO ALEJANDRO DE ARTOLA