4621 1/2-4623 1/2 W PICKFORD ST 90019

Certificate Information: 4621 1/2-4623 1/2 W PICKFORD ST 90019

Application / Permit
21010-10000-02345
Plan Check / Job No.
B21LA08994
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TWO NEW ADU ATTACHED TO EACH OTHER AT REAR OF LOT.
Permit Issued
Issued on 10/29/2021
Issuing Office
Current Status
CofO Issued on 1/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 JOE VO
Corrections Issued 6/30/2021 JOE VO
Quality Review Completed 7/7/2021 MICHAEL PEREZ
Applicant returned to address corrections 10/4/2021 JOE VO
Applicant returned to address corrections 10/19/2021 JOE VO
Plan Check Approved 10/27/2021 JOE VO
Issued 10/29/2021 APPLICANT
CofO in Progress 1/23/2023 CALEB MEISTER
Permit Finaled 1/30/2023 DEROLD HAUFF
CofO Issued 1/30/2023 DEROLD HAUFF
Permit Finaled 1/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 9/4/2021 TA ANH
Address approval Cleared 9/8/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/8/2021 JEANIE LAM
Sewer availability Cleared 9/8/2021 JEANIE LAM
Hydrant and Access approval Cleared 9/13/2021 RUEL COLE
Roof/Waste drainage to street Cleared 9/13/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/1/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 2/8/2022 Approved STUART CHAPMAN
METHANE-Barrier 2/8/2022 Approved STUART CHAPMAN
METHANE-Subgrade 2/8/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 2/23/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Corrections Issued STUART CHAPMAN
Deputy Wood Construction 3/10/2022 Conditional Approval STUART CHAPMAN
BUILDING-Rough-Frame 3/18/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 3/18/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Corrections Issued STUART CHAPMAN
Green Building Rough 3/18/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 3/18/2022 Corrections Issued STUART CHAPMAN
METHANE-Rough 3/18/2022 Approved STUART CHAPMAN
PLUMBING-Rough 3/18/2022 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 3/18/2022 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 3/18/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 4/15/2022 Conditional Approval STUART CHAPMAN
Green Building Rough 4/15/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 4/15/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 4/25/2022 Approved STUART CHAPMAN
Insulation 4/25/2022 Approved STUART CHAPMAN
Drywall Nailing 4/29/2022 Approved STUART CHAPMAN
Shower Pan 4/29/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/8/2022 Partial Approval STUART CHAPMAN
Sewer 6/15/2022 Approved STUART CHAPMAN
Underground Mechanical 9/22/2022 Approved ALEJANDRO DE ARTOLA
Final 11/9/2022 Corrections Issued STUART CHAPMAN
Green Building Final 11/9/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 11/9/2022 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 11/9/2022 Approved STUART CHAPMAN
Final 12/21/2022 Corrections Issued CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Not Required CALEB MEISTER
Service/Power Release 12/21/2022 Not Ready for Inspection CALEB MEISTER
Service/Power Release 1/17/2023 Conditional Approval CALEB MEISTER
Final 1/23/2023 OK to Issue CofO CALEB MEISTER
Service/Power Release 1/23/2023 Approved CALEB MEISTER