4621 1/2-4623 1/2 W PICKFORD ST 90019
Certificate Information: 4621 1/2-4623 1/2 W PICKFORD ST 90019
- Application / Permit
- 21010-10000-02345
- Plan Check / Job No.
- B21LA08994
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- TWO NEW ADU ATTACHED TO EACH OTHER AT REAR OF LOT.
- Permit Issued
- Issued on 10/29/2021
- Issuing Office
- Current Status
- CofO Issued on 1/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | JOE VO |
| Corrections Issued | 6/30/2021 | JOE VO |
| Quality Review Completed | 7/7/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/4/2021 | JOE VO |
| Applicant returned to address corrections | 10/19/2021 | JOE VO |
| Plan Check Approved | 10/27/2021 | JOE VO |
| Issued | 10/29/2021 | APPLICANT |
| CofO in Progress | 1/23/2023 | CALEB MEISTER |
| Permit Finaled | 1/30/2023 | DEROLD HAUFF |
| CofO Issued | 1/30/2023 | DEROLD HAUFF |
| Permit Finaled | 1/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/4/2021 | TA ANH |
| Address approval | Cleared | 9/8/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | JEANIE LAM |
| Sewer availability | Cleared | 9/8/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/13/2021 | RUEL COLE |
| Roof/Waste drainage to street | Cleared | 9/13/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/1/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/8/2022 | Approved | STUART CHAPMAN |
| METHANE-Barrier | 2/8/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 2/8/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 2/23/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Corrections Issued | STUART CHAPMAN |
| Deputy Wood Construction | 3/10/2022 | Conditional Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/18/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 3/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 3/18/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Rough | 3/18/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 3/18/2022 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 3/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/18/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/15/2022 | Conditional Approval | STUART CHAPMAN |
| Green Building Rough | 4/15/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/15/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/25/2022 | Approved | STUART CHAPMAN |
| Insulation | 4/25/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 4/29/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 4/29/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/8/2022 | Partial Approval | STUART CHAPMAN |
| Sewer | 6/15/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 9/22/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/9/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 11/9/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 11/9/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 11/9/2022 | Approved | STUART CHAPMAN |
| Final | 12/21/2022 | Corrections Issued | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Not Required | CALEB MEISTER |
| Service/Power Release | 12/21/2022 | Not Ready for Inspection | CALEB MEISTER |
| Service/Power Release | 1/17/2023 | Conditional Approval | CALEB MEISTER |
| Final | 1/23/2023 | OK to Issue CofO | CALEB MEISTER |
| Service/Power Release | 1/23/2023 | Approved | CALEB MEISTER |