26222 S PRESIDENT AVE 90710
Certificate Information: 26222 S PRESIDENT AVE 90710
- Application / Permit
- 21010-10000-02341
- Plan Check / Job No.
- B21LA08981
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | CARLOS MONTES |
| Corrections Issued | 6/19/2021 | CARLOS MONTES |
| Quality Review Completed | 6/28/2021 | WING SUEN |
| Applicant returned to address corrections | 9/23/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/10/2021 | CARLOS MONTES |
| Plan Check Approved | 1/27/2022 | CARLOS MONTES |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 4/2/2024 | EUGENE CASSIDY |
| Permit Finaled | 4/2/2024 | ANSON MAGLASANG |
| CofO Issued | 4/2/2024 | ANSON MAGLASANG |
| Permit Finaled | 4/2/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2021 | JOSE HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 9/28/2021 | JOSE HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 9/28/2021 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 10/1/2021 | JOSE HERNANDEZ |
| ZA Case | Cleared | 10/12/2021 | TERRI OSBORNE |
| Construction near power lines | Cleared | 10/28/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 11/17/2021 | RUEL COLE |
| Low Impact Development | Cleared | 1/24/2022 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 1/26/2022 | JOSE HERNANDEZ |
| GPI Written Notices | Cleared | 1/27/2022 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 1/27/2022 | CARLOS MONTES |
Contact Information
| Architect | Xolotl,, Steve Reynoso; Lic. No.: C26504 | 503 W 30TH STREET SAN PEDRO, CA 90731 |
| Contractor | M.R Design & Build; Lic. No.: 1072428-B | 2209 MICHIGAN AVE APT 210 LOS ANGELES, CA 90033 |
| Engineer | Hashemi,, Jafar; Lic. No.: C62010 | 26009 CALMHILL DR TORRANCE, CA 90505 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/11/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/18/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/24/2022 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 11/10/2022 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/10/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 12/21/2022 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/26/2023 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 1/26/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 1/26/2023 | Partial Approval | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/26/2023 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 2/13/2023 | Approved | EUGENE CASSIDY |
| Shower Pan | 2/13/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/21/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 2/21/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 3/2/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 3/2/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/10/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/11/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 5/8/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 5/8/2023 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 5/12/2023 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/22/2023 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 7/20/2023 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/26/2023 | Approved | EUGENE CASSIDY |
| Final | 7/26/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/26/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/26/2023 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 7/26/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 7/26/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/1/2023 | Approved | EUGENE CASSIDY |
| Final | 12/1/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 12/1/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 12/1/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/1/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 12/1/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 12/27/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 12/27/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 12/27/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/19/2024 | Approved | EUGENE CASSIDY |
| Final | 3/19/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 3/19/2024 | Approved | EUGENE CASSIDY |
| HVAC-Final | 3/19/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/19/2024 | Approved | EUGENE CASSIDY |
| Service/Power Release | 3/19/2024 | Not Required | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/1/2024 | Approved | EUGENE CASSIDY |
| Final | 4/1/2024 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 4/1/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 4/1/2024 | Approved | EUGENE CASSIDY |