1541 S CLUB VIEW DR 90024
Certificate Information: 1541 S CLUB VIEW DR 90024
- Application / Permit
- 21010-10000-02325
- Plan Check / Job No.
- B21LA08894
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE AND BASEMENT
- Permit Issued
- Issued on 9/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | DANIEL YIP |
| Corrections Issued | 6/24/2021 | DANIEL YIP |
| Quality Review Completed | 7/7/2021 | JASON HEALEY |
| Building Plans Picked Up | 8/16/2021 | APPLICANT |
| Applicant returned to address corrections | 12/1/2021 | DANIEL YIP |
| Applicant returned to address corrections | 5/3/2022 | DANIEL YIP |
| Plan Check Approved | 7/28/2022 | DANIEL YIP |
| Issued | 9/9/2022 | APPLICANT |
| CofO in Progress | 5/21/2025 | DANIEL VERA |
| Permit Finaled | 6/11/2025 | RICHARD STEINBACH |
| CofO Issued | 6/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 12/13/2021 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 2/10/2022 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 2/19/2022 | KURT CORRAL |
| Specific Plan | Cleared | 4/6/2022 | FREDDY GARCIA |
| Low Impact Development | Cleared | 5/31/2022 | KHAING AYE |
| GPI Written Notices | Cleared | 7/28/2022 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 7/28/2022 | DANIEL YIP |
| Roof/Waste drainage to street | Cleared | 7/30/2022 | STEVEN JIN |
| Excavation more than 5-ft deep | Cleared | 8/11/2022 | CALOSHA APPROVED |
Contact Information
| Architect | Prentice,, Scott Charles; Lic. No.: C23183 | PO BOX 518 PACIFIC PALISADES, CA 90272 |
| Contractor | Dixon Construction Inc; Lic. No.: 706524-B | 3169 MOUNTAIN VIEW AVE LOS ANGELES, CA 90066 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/15/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/16/2022 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/30/2022 | Partial Approval | CHRISTOPHER WILSON |
| METHANE-Barrier | 11/30/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Subgrade | 11/30/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 12/15/2022 | Partial Approval | CHRISTOPHER WILSON |
| METHANE-Barrier | 12/15/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Subgrade | 12/15/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 12/20/2022 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 12/20/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 12/20/2022 | Partial Approval | STEPHANIE SWANSON |
| Deputy Methane Barrier | 1/20/2023 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Methane Barrier | 2/21/2023 | Conditional Approval | MICHAEL PELHAM |
| METHANE-Subgrade | 2/27/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 2/27/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Subgrade | 3/1/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/1/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/3/2023 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Methane Barrier | 3/16/2023 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Methane Barrier | 3/17/2023 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 3/22/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 3/22/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Subgrade | 3/22/2023 | Approved | STEPHANIE SWANSON |
| Deputy Methane Barrier | 3/31/2023 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | STEPHANIE SWANSON |
| Wood Frame | 6/14/2023 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Subgrade | 7/20/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/27/2023 | Partial Approval | STEPHANIE SWANSON |
| Pre-Inspection | 11/6/2023 | Partial Inspection | STEPHANIE SWANSON |
| Deputy Methane Barrier | 11/16/2023 | Conditional Approval | MICHAEL PELHAM |
| METHANE-Barrier | 1/9/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 1/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/18/2024 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Deputy Wood Construction | 3/22/2024 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/18/2024 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/24/2024 | Conditional Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/24/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Green Building Rough | 4/24/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/24/2024 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Rough | 4/24/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/24/2024 | Conditional Approval | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 4/24/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/7/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/7/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 5/7/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 5/7/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 5/20/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 5/31/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 6/10/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/26/2024 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/10/2024 | Partial Approval | STEPHANIE SWANSON |
| Gas Test | 10/2/2024 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2024 | SGSOV Approved | MICHAEL ALLEN |
| Sewer | 10/2/2024 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 3/5/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/20/2025 | Corrections Issued | DANIEL VERA |
| HVAC-Final | 3/20/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 3/26/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 3/26/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 4/2/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 4/4/2025 | Approved | DANIEL VERA |
| Final | 4/17/2025 | Corrections Issued | DANIEL VERA |
| Footing/Foundation/Slab | 4/17/2025 | Approved | DANIEL VERA |
| Green Building Final | 4/17/2025 | Approved | DANIEL VERA |
| Service/Power Release | 4/17/2025 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 4/17/2025 | Not Ready for Inspection | DANIEL VERA |
| Sewer | 5/7/2025 | Approved | DANIEL VERA |
| Final | 5/15/2025 | Corrections Issued | DANIEL VERA |
| Service/Power Release | 5/15/2025 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 5/15/2025 | Approved | DANIEL VERA |
| Final | 5/16/2025 | OK to Issue CofO | DANIEL VERA |
| Pre-Inspection | 5/16/2025 | Approved | DANIEL VERA |
| Service/Power Release | 5/16/2025 | Approved | DANIEL VERA |