1773 S PREUSS ROAD 90035
Certificate Information: 1773 S PREUSS ROAD 90035
- Application / Permit
- 21010-10000-02324
- Plan Check / Job No.
- B21LA08891
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING WITH 2-CAR GARAGE
- Permit Issued
- Issued on 11/30/2021
- Issuing Office
- Current Status
- CofO Issued on 12/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | DANIEL YIP |
| Corrections Issued | 6/1/2021 | DANIEL YIP |
| Quality Review Completed | 6/3/2021 | KEN GILL |
| Applicant returned to address corrections | 10/8/2021 | DANIEL YIP |
| Building Plans Picked Up | 10/12/2021 | APPLICANT |
| Plan Check Approved | 10/15/2021 | DANIEL YIP |
| Issued | 11/30/2021 | APPLICANT |
| CofO in Progress | 12/8/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
| CofO Issued | 12/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/13/2021 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2021 | CELINA MORENO |
| Sewer availability | Cleared | 9/1/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 9/13/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/5/2021 | CELINA MORENO |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh Namaghi; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
| Engineer | Kaligi,, Sean; Lic. No.: M37797 | 655 N CENTRAL AVE 17TH FL GLENDALE, CA 91203 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/3/2021 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 12/3/2021 | No Access for Inspection | EVAN COOPER |
| METHANE-Subgrade | 12/3/2021 | No Access for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 12/6/2021 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 12/13/2021 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 12/13/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 12/13/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 12/13/2021 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 12/16/2021 | Conditional Approval | EVAN COOPER |
| METHANE-Subgrade | 12/21/2021 | Approved | EVAN COOPER |
| Deputy Methane Barrier | 1/6/2022 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 1/7/2022 | Approved | EVAN COOPER |
| METHANE-Barrier | 1/7/2022 | Approved | EVAN COOPER |
| Wood Frame | 1/20/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 1/31/2022 | Partial Approval | EVAN COOPER |
| Green Building Rough | 1/31/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 1/31/2022 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 1/31/2022 | Not Ready for Inspection | EVAN COOPER |
| Deputy Wood Construction | 2/14/2022 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 2/17/2022 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 2/17/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 2/17/2022 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 2/17/2022 | Not Ready for Inspection | EVAN COOPER |
| Wood Frame | 2/17/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 3/18/2022 | Corrections Issued | JOHNNY MIRANDA |
| Wood Frame | 3/18/2022 | No Access for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 3/29/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/29/2022 | Partial Approval | EVAN COOPER |
| Wood Frame | 3/29/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 4/8/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 4/8/2022 | Approved | EVAN COOPER |
| Green Building Rough | 4/8/2022 | Approved | EVAN COOPER |
| METHANE-Rough | 4/8/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 4/8/2022 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 4/8/2022 | Approved | EVAN COOPER |
| Insulation | 4/14/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 4/18/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/25/2022 | Approved | STEPHANIE SWANSON |
| Shower Pan | 4/25/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 9/23/2022 | Approved | EVAN COOPER |
| Service/Power Release | 9/23/2022 | Not Ready for Inspection | EVAN COOPER |
| Gas Test | 9/27/2022 | Approved | EVAN COOPER |
| HVAC-Final | 9/27/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 9/27/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 9/28/2022 | Corrections Issued | EVAN COOPER |
| Final | 11/23/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 11/23/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 12/5/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 12/5/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 12/5/2022 | Approved | OGANES TARAKHCHYAN |
| Posting Pre-Inspection | 12/7/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 12/8/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |