2418 S BEVERLY DR 90034

Certificate Information: 2418 S BEVERLY DR 90034

Application / Permit
21010-10000-02303
Plan Check / Job No.
B21LA08808
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WITH 2-CAR GARAGE AND BASEMENT
Permit Issued
Issued on 5/20/2022
Issuing Office
Current Status
CofO Issued on 5/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 DANIEL YIP
Corrections Issued 6/1/2021 DANIEL YIP
Quality Review Completed 6/3/2021 KEN GILL
Applicant returned to address corrections 2/7/2022 DANIEL YIP
Plan Check Approved 4/19/2022 DANIEL YIP
Plan Check Approved 4/27/2022 DANIEL YIP
Issued 5/20/2022 APPLICANT
Building Plans Picked Up 5/23/2022 APPLICANT
CofO in Progress 5/10/2024 OGANES TARAKHCHYAN
Permit Finaled 5/10/2024 DANIEL ORRANTE
CofO Issued 5/10/2024 DANIEL ORRANTE
Permit Finaled 5/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 6/8/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/8/2021 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 8/3/2021 MATTHEW CRAIG
Low Impact Development Cleared 1/24/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 2/1/2022 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 2/7/2022 HISASHI KOBAYAKAWA
Excavation more than 5-ft deep Cleared 2/7/2022 CALOSHA APPROVED
GPI Written Notices Cleared 2/7/2022 DANIEL YIP
Grading Pre-Inspection Cleared 2/7/2022 DANIEL YIP

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Di Nalli Construction; Lic. No.: 942979-B 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Engineer Askarian,, Soroosh Namaghi; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/25/2022 Partial Inspection KEVIN SARGSYAN
Deputy Methane Barrier 9/2/2022 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 9/6/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Methane Barrier 9/12/2022 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 9/13/2022 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 9/14/2022 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 9/15/2022 Conditional Approval RICHARD STEINBACH
Deputy Methane Barrier 9/16/2022 Conditional Approval ANDREW NAVE
Underground Mechanical 11/8/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Methane Barrier 11/16/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Methane Barrier 11/17/2022 Approved MICHAEL PELHAM
Footing/Foundation/Slab 11/22/2022 Approved OGANES TARAKHCHYAN
METHANE-Barrier 11/22/2022 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 11/22/2022 Approved OGANES TARAKHCHYAN
Reinforced Concrete Frame 12/5/2022 Approved OGANES TARAKHCHYAN
Deputy Shotcrete 12/8/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 2/17/2023 Corrections Issued ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 3/3/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 3/20/2023 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 3/31/2023 Not Ready for Inspection JEREMY TODD
Excavation/Setback/Form/Re-Bar 4/4/2023 Partial Approval ASHLEY THOMPSON
Deputy Methane Barrier 4/10/2023 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 4/11/2023 Approved ASHLEY THOMPSON
METHANE-Rough 4/11/2023 Not Ready for Inspection ASHLEY THOMPSON
Wood Frame 4/21/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Approval CLAYTON GRAHAM
Deputy Wood Construction 6/9/2023 Conditional Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Partial Approval CLAYTON GRAHAM
HVAC-Rough 7/3/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 7/5/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Rough 7/6/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Rough 7/11/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 7/11/2023 Not Ready for Inspection CLAYTON GRAHAM
PLUMBING-Rough 7/11/2023 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 7/21/2023 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 7/21/2023 Not Ready for Inspection CLAYTON GRAHAM
Green Building Rough 7/21/2023 Not Ready for Inspection CLAYTON GRAHAM
Interior/Exterior Lathing 7/21/2023 Approved CLAYTON GRAHAM
METHANE-Rough 7/21/2023 Approved CLAYTON GRAHAM
Special/Order Compliance 7/21/2023 Corrections Issued CLAYTON GRAHAM
Verify Sprinkler Sign Off 7/21/2023 Not Ready for Inspection CLAYTON GRAHAM
Insulation 7/24/2023 Corrections Issued CLAYTON GRAHAM
Shower Pan 7/24/2023 Approved CLAYTON GRAHAM
Verify Sprinkler Sign Off 7/24/2023 Approved CLAYTON GRAHAM
Insulation 7/27/2023 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 8/2/2023 Approved CLAYTON GRAHAM
Drywall Nailing 8/2/2023 Approved CLAYTON GRAHAM
Green Building Rough 8/2/2023 Approved CLAYTON GRAHAM
HVAC-Final 1/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 1/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 1/17/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 2/23/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 2/23/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 2/28/2024 Approved MEL KHACHATOURIAN
PLUMBING-Final 2/28/2024 Approved MEL KHACHATOURIAN
Final 4/25/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 4/25/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 4/25/2024 Approved OGANES TARAKHCHYAN
Final 5/9/2024 OK to Issue CofO OGANES TARAKHCHYAN
PLUMBING-Final 5/9/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 5/9/2024 Approved OGANES TARAKHCHYAN