2418 S BEVERLY DR 90034
Certificate Information: 2418 S BEVERLY DR 90034
- Application / Permit
- 21010-10000-02303
- Plan Check / Job No.
- B21LA08808
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING WITH 2-CAR GARAGE AND BASEMENT
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Current Status
- CofO Issued on 5/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | DANIEL YIP |
| Corrections Issued | 6/1/2021 | DANIEL YIP |
| Quality Review Completed | 6/3/2021 | KEN GILL |
| Applicant returned to address corrections | 2/7/2022 | DANIEL YIP |
| Plan Check Approved | 4/19/2022 | DANIEL YIP |
| Plan Check Approved | 4/27/2022 | DANIEL YIP |
| Issued | 5/20/2022 | APPLICANT |
| Building Plans Picked Up | 5/23/2022 | APPLICANT |
| CofO in Progress | 5/10/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 5/10/2024 | DANIEL ORRANTE |
| CofO Issued | 5/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 6/8/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/8/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 8/3/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/24/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 2/1/2022 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | HISASHI KOBAYAKAWA |
| Excavation more than 5-ft deep | Cleared | 2/7/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 2/7/2022 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 2/7/2022 | DANIEL YIP |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh Namaghi; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/25/2022 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Methane Barrier | 9/2/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 9/6/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 9/12/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 9/13/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 9/14/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 9/15/2022 | Conditional Approval | RICHARD STEINBACH |
| Deputy Methane Barrier | 9/16/2022 | Conditional Approval | ANDREW NAVE |
| Underground Mechanical | 11/8/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 11/16/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 11/17/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/22/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Barrier | 11/22/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 11/22/2022 | Approved | OGANES TARAKHCHYAN |
| Reinforced Concrete Frame | 12/5/2022 | Approved | OGANES TARAKHCHYAN |
| Deputy Shotcrete | 12/8/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/17/2023 | Corrections Issued | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 3/3/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 3/20/2023 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 3/31/2023 | Not Ready for Inspection | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Partial Approval | ASHLEY THOMPSON |
| Deputy Methane Barrier | 4/10/2023 | Conditional Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 4/11/2023 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 4/11/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Wood Frame | 4/21/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Partial Approval | CLAYTON GRAHAM |
| Deputy Wood Construction | 6/9/2023 | Conditional Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | CLAYTON GRAHAM |
| HVAC-Rough | 7/3/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 7/5/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 7/6/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 7/11/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/11/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 7/11/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 7/21/2023 | Partial Approval | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 7/21/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Rough | 7/21/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/21/2023 | Approved | CLAYTON GRAHAM |
| METHANE-Rough | 7/21/2023 | Approved | CLAYTON GRAHAM |
| Special/Order Compliance | 7/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 7/21/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Insulation | 7/24/2023 | Corrections Issued | CLAYTON GRAHAM |
| Shower Pan | 7/24/2023 | Approved | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 7/24/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 7/27/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 8/2/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 8/2/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 8/2/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 1/9/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 1/9/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 1/17/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 2/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 2/23/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 2/28/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 2/28/2024 | Approved | MEL KHACHATOURIAN |
| Final | 4/25/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 4/25/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Service/Power Release | 4/25/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 5/9/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| PLUMBING-Final | 5/9/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 5/9/2024 | Approved | OGANES TARAKHCHYAN |