1519 W 218TH ST 90501

Certificate Information: 1519 W 218TH ST 90501

Application / Permit
21010-10000-02285
Plan Check / Job No.
B21LA08723
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 28'-11"X48' 2-STORY SECOND SFD 2,212 SF W/ ATTACHED 2-CAR GARAGE 607 SF. 1 OF 2
Permit Issued
Issued on 11/17/2022
Issuing Office
San Pedro
Current Status
CofO Issued on 2/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 CHUNG-WEN CHUANG
Corrections Issued 7/13/2021 CHUNG-WEN CHUANG
Quality Review Completed 7/22/2021 ALLEN MANALANSAN
Building Plans Picked Up 7/30/2021 APPLICANT
Applicant returned to address corrections 12/15/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 12/29/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 1/10/2022 CHUNG-WEN CHUANG
Plan Check Approved 10/25/2022 CHUNG-WEN CHUANG
Issued 11/17/2022 APPLICANT
CofO in Progress 2/24/2026 EUGENE CASSIDY
Permit Finaled 2/25/2026 ANSON MAGLASANG
CofO Issued 2/25/2026 ANSON MAGLASANG
Permit Finaled 2/25/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 4/7/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 4/25/2022 JOSE HERNANDEZ
Hydrant and Access approval Cleared 4/26/2022 DWIGHT SANKEY
Low Impact Development Cleared 7/14/2022 SUNG JOON WON
Sewer availability Cleared 9/29/2022 JOSE HERNANDEZ
Roof/Waste drainage to street Cleared 10/3/2022 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/5/2022 Approved JOHN KLARIN
PLUMBING-Rough 12/5/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 12/14/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 1/31/2023 Corrections Issued EUGENE CASSIDY
Green Building Rough 1/31/2023 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 1/31/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 3/22/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/22/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 3/28/2023 Corrections Issued EUGENE CASSIDY
Green Building Rough 3/28/2023 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 3/28/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 3/28/2023 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 3/28/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/24/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/24/2023 Approved EUGENE CASSIDY
Green Building Rough 4/24/2023 Approved EUGENE CASSIDY
HVAC-Rough 4/24/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/24/2023 Partial Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 4/24/2023 Approved EUGENE CASSIDY
Insulation 4/28/2023 Approved EUGENE CASSIDY
Drywall Nailing 5/16/2023 Approved EUGENE CASSIDY
Final 3/17/2025 Corrections Issued EUGENE CASSIDY
Final 8/11/2025 Corrections Issued EUGENE CASSIDY
Gas Test 8/11/2025 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 8/11/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 8/11/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 8/11/2025 Approved EUGENE CASSIDY
Final 11/26/2025 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Approved EUGENE CASSIDY
Service/Power Release 11/26/2025 Not Ready for Inspection EUGENE CASSIDY
Final 2/9/2026 Corrections Issued EUGENE CASSIDY
Service/Power Release 2/9/2026 Not Ready for Inspection EUGENE CASSIDY
Final 2/23/2026 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 2/23/2026 Not Required EUGENE CASSIDY