4512 N SUNNYSLOPE AVE 91423

Certificate Information: 4512 N SUNNYSLOPE AVE 91423

Application / Permit
21010-10000-02281
Plan Check / Job No.
B21LA08671
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SINGLE FAMILY DWELLING W/ATTACHED GARAGE. FULLY SPRINKLERED THROUGHOUT.
Permit Issued
Issued on 1/24/2022
Issuing Office
Current Status
CofO Issued on 4/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 ZAW HAN
Corrections Issued 5/17/2021 ZAW HAN
Applicant returned to address corrections 7/22/2021 RICARDO RAMIREZ
Applicant returned to address corrections 11/2/2021 LUIS RINCON
Plan Check Approved 11/22/2021 RICARDO RAMIREZ
Building Plans Picked Up 11/23/2021 APPLICANT
Plan Check Approved 1/11/2022 JON BLAINE
Issued 1/24/2022 APPLICANT
CofO in Progress 3/20/2023 MISAEL ESPARZA
CofO Issued 4/3/2023 MICHAEL SMITH
Permit Finaled 4/3/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/24/2021 GABRIEL ROBLES
Permit Cleared 5/24/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/18/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 7/26/2021 ROBERT DUFF
Sewer availability Cleared 7/30/2021 GABRIEL ROBLES
ZI Cleared 8/23/2021 RUBEN VASQUEZ
Frnt yard landscape/Water mgmt Cleared 9/15/2021 RUBEN VASQUEZ
Low Impact Development Cleared 10/6/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 10/14/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361
Landscape Architect Alaniz,, Arthur Louis; Lic. No.: LA5554 26 CLEAR VISTA      ROLLING HILLS ESTATES, CA 90274

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/8/2022 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/18/2022 Approved MISAEL ESPARZA
HVAC-Rough 3/18/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/18/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 3/30/2022 Approved MISAEL ESPARZA
HVAC-Rough 3/30/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/30/2022 Approved MISAEL ESPARZA
HVAC-Rough 4/7/2022 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 4/7/2022 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 4/11/2022 Partial Approval MISAEL ESPARZA
Shower Pan 4/11/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/15/2022 No Access for Inspection MISAEL ESPARZA
Green Building Rough 4/15/2022 No Access for Inspection MISAEL ESPARZA
HVAC-Rough 4/15/2022 No Access for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 4/15/2022 No Access for Inspection MISAEL ESPARZA
HVAC-Rough 4/18/2022 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 4/18/2022 Partial Approval MISAEL ESPARZA
Wood Frame 4/18/2022 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 4/26/2022 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 5/3/2022 Approved MISAEL ESPARZA
Green Building Rough 5/3/2022 Approved MISAEL ESPARZA
HVAC-Rough 5/3/2022 Approved MISAEL ESPARZA
Insulation 5/3/2022 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 5/3/2022 Approved MISAEL ESPARZA
Drywall Nailing 5/16/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/18/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 11/18/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/28/2022 Partial Approval MISAEL ESPARZA
ELECTRICAL-Final 2/10/2023 Corrections Issued MISAEL ESPARZA
HVAC-Final 2/10/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 2/10/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 2/27/2023 Approved MISAEL ESPARZA
HVAC-Final 2/27/2023 Approved MISAEL ESPARZA
PLUMBING-Final 2/27/2023 Approved MISAEL ESPARZA
Final 3/17/2023 OK to Issue CofO MISAEL ESPARZA
Footing/Foundation/Slab 3/17/2023 Approved MISAEL ESPARZA
Green Building Final 3/17/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 3/17/2023 Approved MISAEL ESPARZA
Smoke Detectors 3/17/2023 Approved MISAEL ESPARZA