1755 S INDUSTRIAL WAY 90023

Certificate Information: 1755 S INDUSTRIAL WAY 90023

Application / Permit
21010-10000-02255
Plan Check / Job No.
B17LA06472
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
new office and restroom buildingfor use of land use of recycling
Permit Issued
Issued on 7/19/2021
Issuing Office
Current Status
Issued on 7/19/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/20/2017 APPLICANT
Assigned to Plan Check Engineer 5/11/2017 AUNG SOE
Corrections Issued 5/15/2017 SHUNYU ZHANG
Quality Review Completed 5/16/2017 BINH PHAN
Building Plans Picked Up 7/11/2017 APPLICANT
Applicant returned to address corrections 6/11/2018 SAM CHANG
Applicant returned to address corrections 9/26/2019 SAM CHANG
Applicant returned to address corrections 3/23/2021 SAM CHANG
Plan Check Approved 5/4/2021 SAM CHANG
Plan Check Approved 5/27/2021 SAM CHANG
Issued 7/19/2021 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/28/2022 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 2/28/2023 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 5/1/2023 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 4/19/2024 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 5/29/2024 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 8/2/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 8/2/2024 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 8/12/2024 Approved RONALD JIMENEZ
Wood Frame 8/12/2024 Partial Approval RONALD JIMENEZ
Final 9/11/2024 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 9/11/2024 Approved LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 9/11/2024 SGSOV Not Ready LARRY ARNICK
Wood Frame 9/11/2024 Approved LARRY ARNICK
Insulation 10/15/2024 Approved LARRY ARNICK
Final 10/30/2024 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Not Ready LARRY ARNICK
Pre-Inspection 12/4/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/27/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 1/30/2025 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 1/31/2025 Approved LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Partial Approval RAFAEL CORTES
Final 6/9/2025 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Not Ready RAFAEL CORTES