1755 S INDUSTRIAL WAY 90023
Certificate Information: 1755 S INDUSTRIAL WAY 90023
- Application / Permit
- 21010-10000-02255
- Plan Check / Job No.
- B17LA06472
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- new office and restroom buildingfor use of land use of recycling
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- Issued on 7/19/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/20/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2017 | AUNG SOE |
| Corrections Issued | 5/15/2017 | SHUNYU ZHANG |
| Quality Review Completed | 5/16/2017 | BINH PHAN |
| Building Plans Picked Up | 7/11/2017 | APPLICANT |
| Applicant returned to address corrections | 6/11/2018 | SAM CHANG |
| Applicant returned to address corrections | 9/26/2019 | SAM CHANG |
| Applicant returned to address corrections | 3/23/2021 | SAM CHANG |
| Plan Check Approved | 5/4/2021 | SAM CHANG |
| Plan Check Approved | 5/27/2021 | SAM CHANG |
| Issued | 7/19/2021 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 2/28/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 5/1/2023 | Corrections Issued | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 4/19/2024 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 5/29/2024 | Partial Approval | LARRY ARNICK |
| Verify Sprinkler Sign Off | 8/2/2024 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 8/2/2024 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 8/12/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 8/12/2024 | Partial Approval | RONALD JIMENEZ |
| Final | 9/11/2024 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 9/11/2024 | Approved | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Not Ready | LARRY ARNICK |
| Wood Frame | 9/11/2024 | Approved | LARRY ARNICK |
| Insulation | 10/15/2024 | Approved | LARRY ARNICK |
| Final | 10/30/2024 | Not Ready for Inspection | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 10/30/2024 | SGSOV Not Ready | LARRY ARNICK |
| Pre-Inspection | 12/4/2024 | Not Ready for Inspection | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 1/27/2025 | Not Ready for Inspection | LARRY ARNICK |
| Reinforced Concrete Frame | 1/30/2025 | Partial Approval | LARRY ARNICK |
| Reinforced Concrete Frame | 1/31/2025 | Approved | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Partial Approval | RAFAEL CORTES |
| Final | 6/9/2025 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Not Ready | RAFAEL CORTES |