1643 W 222ND ST 90501

Certificate Information: 1643 W 222ND ST 90501

Application / Permit
21010-10000-02248
Plan Check / Job No.
B21LA08502
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU (1110 SF) WITH PORCH (92) PER ORDINANCE (1-STORY )
Permit Issued
Issued on 12/2/2022
Issuing Office
Current Status
CofO Issued on 1/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 CARLOS MONTES
Corrections Issued 6/23/2021 CARLOS MONTES
Quality Review Completed 6/30/2021 WING SUEN
Plan Check Approved 11/2/2022 CARLOS MONTES
Issued 12/2/2022 APPLICANT
CofO in Progress 12/15/2023 EUGENE CASSIDY
Permit Finaled 1/2/2024 ANSON MAGLASANG
CofO Issued 1/2/2024 ANSON MAGLASANG
Permit Finaled 1/2/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 8/10/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 10/8/2021 JOSE HERNANDEZ
Sewer availability Cleared 10/8/2021 JOSE HERNANDEZ
Hydrant and Access approval Cleared 1/3/2022 GILBERT URREA
Low Impact Development Cleared 8/4/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 9/7/2022 JOSE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 12/21/2022 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 12/27/2022 Corrections Issued JOHN KLARIN
METHANE-Barrier 12/27/2022 Approved JOHN KLARIN
METHANE-Subgrade 12/27/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 1/5/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 1/10/2023 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 1/12/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Approved JAMES CHAVEZ
Underground Mechanical 1/31/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Not Ready for Inspection EUGENE CASSIDY
Insulation 2/2/2023 Approved EUGENE CASSIDY
Pre-Inspection 2/6/2023 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/28/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 4/28/2023 Not Ready for Inspection EUGENE CASSIDY
Gas Test 4/28/2023 Approved EUGENE CASSIDY
Light Gage Steel Frame 4/28/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/28/2023 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 4/28/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/2/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 5/2/2023 Approved EUGENE CASSIDY
HVAC-Rough 5/2/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 5/2/2023 Approved EUGENE CASSIDY
Insulation 5/15/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/15/2023 Partial Approval EUGENE CASSIDY
Drywall Nailing 5/22/2023 Approved EUGENE CASSIDY
Green Building Rough 5/22/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/22/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
Final 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Final 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 8/28/2023 Corrections Issued EUGENE CASSIDY
Verify Sprinkler Sign Off 8/28/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 8/31/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/31/2023 Not Ready for Inspection EUGENE CASSIDY
Final 8/31/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/31/2023 Approved EUGENE CASSIDY
Green Building Final 8/31/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Final 8/31/2023 Approved EUGENE CASSIDY
METHANE-Rough 8/31/2023 Approved EUGENE CASSIDY
PLUMBING-Final 8/31/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 8/31/2023 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 8/31/2023 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 8/31/2023 Approved EUGENE CASSIDY
Final 12/1/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 12/1/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 12/1/2023 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 12/1/2023 Not Ready for Inspection EUGENE CASSIDY
Final 12/6/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 12/6/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/6/2023 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 12/6/2023 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 12/6/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 12/14/2023 Approved EUGENE CASSIDY
Final 12/14/2023 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 12/14/2023 Approved EUGENE CASSIDY
PLUMBING-Final 12/14/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/14/2023 SGSOV Approved EUGENE CASSIDY
Service/Power Release 12/14/2023 Approved EUGENE CASSIDY