14810 W ADDISON ST 91403

Certificate Information: 14810 W ADDISON ST 91403

Application / Permit
21010-10000-02229
Plan Check / Job No.
B21LA08424
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. New 559 sq.ft Accessory Dwelling Unit
Permit Issued
Issued on 10/1/2021
Issuing Office
Current Status
CofO in Progress on 11/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/5/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 ARSALAN SHABESTARI
Corrections Issued 5/22/2021 ARSALAN SHABESTARI
Quality Review Completed 6/4/2021 MICHAEL PEREZ
Applicant returned to address corrections 6/28/2021 ARSALAN SHABESTARI
Plan Check Approved 9/22/2021 ARSALAN SHABESTARI
Issued 10/1/2021 APPLICANT
CofO in Progress 11/8/2024 JACK KARGODORIAN
CofO in Progress 11/8/2024 RAUL OLAGI

Permit Application Clearance Information

Address approval Cleared 6/8/2021 CARLOS AGUILERA
ZI Cleared 6/8/2021 PABLO ESTRADA
Construction near power lines Cleared 6/19/2021 WALTER RAMIREZ
Construction within easement Cleared 6/19/2021 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 6/21/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 8/27/2021 MATTHEW CRAIG
Low Impact Development Cleared 9/2/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 9/7/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/13/2021 ABDULLAH SADOZAI

Contact Information

Contractor H & O Unique Construction Inc; Lic. No.: 1016124-B 16350 VENTURA BLVD #D106      ENCINO, CA 91436

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/13/2021 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 10/18/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 11/18/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 11/18/2021 Approved JACK KARGODORIAN
Green Building Rough 11/18/2021 Approved JACK KARGODORIAN
MERV13>=Rough 11/18/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 11/18/2021 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 11/18/2021 Approved JACK KARGODORIAN
Insulation 12/1/2021 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 12/1/2021 Partial Approval JACK KARGODORIAN
Drywall Nailing 12/8/2021 Approved JACK KARGODORIAN
Final 3/17/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 3/17/2022 Approved JACK KARGODORIAN
MERV13>=Final 3/17/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Not Ready JACK KARGODORIAN
Service/Power Release 3/17/2022 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 3/17/2022 Approved JACK KARGODORIAN
Final 3/22/2022 Corrections Issued MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Approved MICHAEL TEMPLE
Service/Power Release 3/22/2022 Not Ready for Inspection MICHAEL TEMPLE
Special/Order Compliance 7/31/2024 Approved STUART CHAPMAN
Final 11/8/2024 Corrections Issued JACK KARGODORIAN
Service/Power Release 11/8/2024 Approved JACK KARGODORIAN
Special/Order Compliance 11/13/2024 Corrections Issued JACK KARGODORIAN
Pre-Inspection 2/11/2025 Approved JACK KARGODORIAN
Special/Order Compliance 3/13/2026 Corrections Issued MICHAEL CORTEZ
Final 4/14/2026 Corrections Issued MICHAEL CORTEZ
Final 5/8/2026 Corrections Issued MICHAEL CORTEZ