7022 N CREBS AVE 91335

Certificate Information: 7022 N CREBS AVE 91335

Application / Permit
21010-10000-02228
Plan Check / Job No.
B21LA08422
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE, ALL WORK TO BE DONE PER WFPP. (1-STORY)
Permit Issued
Issued on 9/16/2021
Issuing Office
Current Status
CofO Issued on 4/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 CARLOS MONTES
Corrections Issued 5/22/2021 CARLOS MONTES
Quality Review Completed 6/1/2021 WING SUEN
Applicant returned to address corrections 8/20/2021 CARLOS MONTES
Plan Check Approved 9/3/2021 CARLOS MONTES
Issued 9/16/2021 APPLICANT
CofO in Progress 4/15/2022 VINCENT HANLEY
CofO Issued 4/15/2022 MICHAEL SMITH
Permit Finaled 4/15/2022 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 6/16/2021 LAUREN PADICK
Address approval Cleared 6/17/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/21/2021 CARLOS AGUILERA
Sewer availability Cleared 6/21/2021 CARLOS AGUILERA
Low Impact Development Cleared 8/10/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/10/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/15/2021 KURT CORRAL
Hold Cleared 9/27/2021 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/20/2021 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/28/2021 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 9/28/2021 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/5/2021 Partial Approval VINCENT HANLEY
HVAC-Rough 11/5/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/5/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 11/5/2021 Not Ready for Inspection VINCENT HANLEY
Rough-Elec/Plmb/HVAC 11/10/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 12/7/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/7/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Approved VINCENT HANLEY
Green Building Rough 12/7/2021 Approved VINCENT HANLEY
HVAC-Rough 12/7/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/7/2021 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 12/7/2021 Not Ready for Inspection VINCENT HANLEY
Insulation 12/14/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/14/2021 Partial Approval JUSTIN HAWLEY
Shower Pan 12/14/2021 Approved JUSTIN HAWLEY
Drywall Nailing 12/20/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/20/2021 Approved JUSTIN HAWLEY
Gas Test 2/3/2022 Approved JUSTIN HAWLEY
Underground Mechanical 2/3/2022 Approved JUSTIN HAWLEY
ELECTRICAL-Final 3/8/2022 Approved VINCENT HANLEY
Final 3/8/2022 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 3/8/2022 Corrections Issued VINCENT HANLEY
Green Building Final 3/8/2022 Approved VINCENT HANLEY
HVAC-Final 3/8/2022 Approved VINCENT HANLEY
PLUMBING-Final 3/8/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 3/8/2022 Approved VINCENT HANLEY
Smoke Detectors 3/8/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 4/8/2022 Approved VINCENT HANLEY
Final 4/8/2022 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 4/8/2022 Approved VINCENT HANLEY
HVAC-Final 4/8/2022 Approved VINCENT HANLEY
PLUMBING-Final 4/8/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 4/14/2022 Approved VINCENT HANLEY
Final 4/14/2022 OK to Issue CofO VINCENT HANLEY
HVAC-Final 4/14/2022 Approved VINCENT HANLEY
PLUMBING-Final 4/14/2022 Approved VINCENT HANLEY