345 1/2 E 93RD ST 90003
Certificate Information: 345 1/2 E 93RD ST 90003
- Application / Permit
- 21010-10000-02226
- Plan Check / Job No.
- B21LA08411
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- CofO Issued on 12/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2021 | KEVIN MORALES |
| Corrections Issued | 8/9/2021 | KEVIN MORALES |
| Plan Check Approved | 5/11/2022 | KEVIN MORALES |
| Issued | 5/12/2022 | APPLICANT |
| CofO in Progress | 12/16/2022 | LILIANA PORTILLO |
| CofO Issued | 12/28/2022 | DEROLD HAUFF |
| Permit Finaled | 12/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | THOMAS LANG |
| Sewer availability | Cleared | 8/18/2021 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 3/1/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 4/1/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 4/5/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/31/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 6/7/2022 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/10/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Partial Approval | LILIANA PORTILLO |
| Insulation | 6/15/2022 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 7/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 7/11/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/18/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/18/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 7/18/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 7/18/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 7/18/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 7/18/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 7/26/2022 | Approved | ADAM ESCOTO |
| Insulation | 7/26/2022 | Approved | ADAM ESCOTO |
| Drywall Nailing | 8/4/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/4/2022 | Approved | LILIANA PORTILLO |
| Sewer | 9/19/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 9/19/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/27/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 10/27/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 10/27/2022 | Corrections Issued | LILIANA PORTILLO |
| Service/Power Release | 10/27/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/18/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 11/18/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 11/18/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 11/18/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 11/18/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 11/18/2022 | Approved | LILIANA PORTILLO |
| Final | 12/8/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 12/8/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 12/8/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 12/8/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/15/2022 | Approved | LILIANA PORTILLO |
| Final | 12/15/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 12/15/2022 | Approved | LILIANA PORTILLO |