3817-3817 1/2 S MOORE ST 90066
Certificate Information: 3817-3817 1/2 S MOORE ST 90066
- Application / Permit
- 21010-10000-02192
- Plan Check / Job No.
- B21LA08258
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX WITH ATTACHED GARAGE (FRONT)
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 7/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | KHEDER ALRAZAA |
| Corrections Issued | 6/17/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 6/28/2021 | JASON HEALEY |
| Applicant returned to address corrections | 8/17/2021 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 10/4/2021 | KHEDER ALRAZAA |
| Building Plans Picked Up | 10/5/2021 | APPLICANT |
| Applicant returned to address corrections | 12/23/2021 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 2/18/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 3/11/2022 | KHEDER ALRAZAA |
| Issued | 4/1/2022 | APPLICANT |
| CofO in Progress | 7/12/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 7/14/2023 | DANIEL ORRANTE |
| CofO Issued | 7/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 7/15/2021 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | NIKTA MOUSAVI |
| Specific Plan | Cleared | 7/22/2021 | KEVIN ARUCAN |
| Address approval | Cleared | 7/26/2021 | NIKTA MOUSAVI |
| Trees in Parkway | Cleared | 7/28/2021 | JOHN KIM |
| Sewer availability | Cleared | 8/1/2021 | NIKTA MOUSAVI |
| Miscellaneous | Cleared | 8/13/2021 | RAYMOND MUGAMBWA |
| Construction near power lines | Cleared | 9/7/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 9/7/2021 | KURT CORRAL |
| Permit | Cleared | 9/9/2021 | NIKTA MOUSAVI |
| Low Impact Development | Cleared | 11/12/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | NIKTA MOUSAVI |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | Inhance Construction Inc; Lic. No.: 1073871-B | 7257 BEVERLY RD STE 205 LOS ANGELES, CA 90036 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
| Landscape Architect | Macias,, Jaime; Lic. No.: LA5870 | 953 FLORE STREET ANAHEIM, CA 92802 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2022 | Partial Approval | PATRICK QUALEY |
| PLUMBING-Rough | 4/11/2022 | Partial Approval | PATRICK QUALEY |
| Pre-Inspection | 4/11/2022 | Partial Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/25/2022 | Conditional Approval | PATRICK QUALEY |
| Grounding or Bonding | 4/25/2022 | Partial Approval | PATRICK QUALEY |
| Deputy Reinf. Concrete | 4/26/2022 | No Access for Inspection | PATRICK QUALEY |
| Deputy Steel/Welding | 4/28/2022 | No Access for Inspection | PATRICK QUALEY |
| Deputy Reinf. Concrete | 5/9/2022 | No Access for Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 5/12/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/18/2022 | Conditional Approval | PATRICK QUALEY |
| Deputy Steel/Welding | 6/2/2022 | No Access for Inspection | PATRICK QUALEY |
| Deputy Wood Construction | 6/13/2022 | No Access for Inspection | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Wood Construction | 6/27/2022 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 8/26/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 9/1/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 9/1/2022 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/1/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 9/8/2022 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 9/9/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Shower Pan | 9/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/16/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 9/16/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 9/16/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/29/2022 | Partial Approval | JESUS RODRIGUEZ |
| Final | 9/29/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 9/29/2022 | Partial Approval | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/14/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/14/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 12/22/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 5/17/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 5/17/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 5/25/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Service/Power Release | 5/25/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 5/25/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Final | 6/29/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 6/29/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 6/29/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Structural Steel Frame | 6/29/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/10/2023 | Approved | JESUS RODRIGUEZ |
| Final | 7/10/2023 | Partial Approval | JESUS RODRIGUEZ |
| Service/Power Release | 7/10/2023 | Approved | JESUS RODRIGUEZ |
| Structural Steel Frame | 7/10/2023 | Approved | JESUS RODRIGUEZ |