468 N HOMEWOOD ROAD 90049

Certificate Information: 468 N HOMEWOOD ROAD 90049

Application / Permit
21010-10000-02173
Plan Check / Job No.
B21LA08177
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY ADU PER CA GOVT CODE 65852.2(E)(1)(B)
Permit Issued
Issued on 11/18/2021
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 STARR CHEN
Corrections Issued 5/23/2021 STARR CHEN
Quality Review Completed 6/1/2021 JASON HEALEY
Applicant returned to address corrections 9/16/2021 STARR CHEN
Plan Check Approved 11/12/2021 STARR CHEN
Issued 11/18/2021 APPLICANT
Building Plans Picked Up 11/22/2021 APPLICANT
CofO in Progress 10/6/2022 JUAN VALENZUELA
Permit Finaled 10/28/2022 DANIEL ORRANTE
CofO Issued 10/28/2022 DANIEL ORRANTE
Permit Finaled 10/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/1/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/2/2021 DINAH GARIN
Sewer availability Cleared 6/2/2021 DINAH GARIN
Watercourse Cleared 6/3/2021 MAHELET GEBEYHU
Hydrant and Access approval Cleared 7/21/2021 KURT CORRAL
Construction near power lines Cleared 9/9/2021 WALTER RAMIREZ
GPI Written Notices Cleared 9/16/2021 STARR CHEN
Grading Pre-Inspection Cleared 9/16/2021 STARR CHEN
Low Impact Development Cleared 10/16/2021 TA ANH
Roof/Waste drainage to street Cleared 10/20/2021 SAUL GARCIA

Contact Information

Contractor Lattanzi Construction Incorporated; Lic. No.: 786592-B P O BOX 49936      LOS ANGELES, CA 90049
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/11/2022 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 1/11/2022 Corrections Issued JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 1/12/2022 Approved JUAN VALENZUELA
Underground Mechanical 1/14/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/19/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/3/2022 Partial Inspection JUAN VALENZUELA
Underground Mechanical 2/9/2022 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 3/25/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 3/25/2022 Partial Approval JUAN VALENZUELA
HVAC-Rough 3/25/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 3/25/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 4/22/2022 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 4/25/2022 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 5/12/2022 Approved JUAN VALENZUELA
FLOOD-Proofing Certificate 5/12/2022 Approved JUAN VALENZUELA
Green Building Rough 5/12/2022 Approved JUAN VALENZUELA
Insulation 5/12/2022 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 5/12/2022 Approved JUAN VALENZUELA
Drywall Nailing 5/19/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 5/31/2022 Approved JUAN VALENZUELA
Shower Pan 5/31/2022 Approved JUAN VALENZUELA
Final 8/31/2022 Corrections Issued JUAN VALENZUELA
Green Building Final 8/31/2022 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved JUAN VALENZUELA
Service/Power Release 8/31/2022 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 8/31/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 10/6/2022 Approved JUAN VALENZUELA
Final 10/6/2022 OK to Issue CofO JUAN VALENZUELA
Green Building Final 10/6/2022 Approved JUAN VALENZUELA
HVAC-Final 10/6/2022 Approved JUAN VALENZUELA
PLUMBING-Final 10/6/2022 Approved JUAN VALENZUELA
Service/Power Release 10/6/2022 Approved JUAN VALENZUELA