460 N ALFRED ST 90048
Certificate Information: 460 N ALFRED ST 90048
- Application / Permit
- 21010-10000-02172
- Plan Check / Job No.
- B21LA08173
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN: NEW DETACHED TWO STORY ADU.
- Permit Issued
- Issued on 8/24/2022
- Issuing Office
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 6/10/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/21/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 9/24/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 1/25/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 6/16/2022 | ARSALAN SHABESTARI |
| Issued | 8/24/2022 | APPLICANT |
| CofO in Progress | 5/7/2024 | AMIR NAZARIAN |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
| CofO Issued | 5/22/2024 | DEROLD HAUFF |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/7/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/13/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/4/2022 | LONDY ALVARADO |
| Hydrant and Access approval | Cleared | 5/9/2022 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 5/10/2022 | JEANETTE VONG |
Contact Information
| Contractor | B H C; Lic. No.: 960037-B | 4607 LAKEVIEW CANYON RD #595 WESTLAKE VILLAGE, CA 91361 |
| Engineer | , ; Lic. No.: NA66957 | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2022 | Partial Approval | MICHAEL LEWIS |
| METHANE-Barrier | 11/4/2022 | Not Ready for Inspection | MICHAEL LEWIS |
| METHANE-Subgrade | 11/4/2022 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 11/4/2022 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/16/2022 | Approved | MICHAEL LEWIS |
| METHANE-Barrier | 11/16/2022 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 11/16/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 1/4/2023 | Approved | MICHAEL LEWIS |
| Sewer | 1/4/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 1/4/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 2/22/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 2/22/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/24/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 2/24/2023 | Corrections Issued | MICHAEL LEWIS |
| METHANE-Rough | 2/24/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 2/24/2023 | Approved | MICHAEL LEWIS |
| Insulation | 3/7/2023 | Corrections Issued | RICHARD DOCKUS |
| Green Building Rough | 3/16/2023 | Approved | MICHAEL LEWIS |
| Insulation | 3/16/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 3/16/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 3/21/2023 | Approved | MICHAEL LEWIS |
| Final | 7/26/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 7/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/26/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 7/26/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/26/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/23/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 10/23/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 10/23/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 11/21/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 11/21/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 11/21/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 11/21/2023 | Approved | LILIANA PORTILLO |
| Service/Power Release | 11/21/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 2/7/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 2/7/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 3/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Service/Power Release | 3/27/2024 | No Access for Inspection | AMIR NAZARIAN |
| Final | 4/1/2024 | Corrections Issued | AMIR NAZARIAN |
| Service/Power Release | 4/1/2024 | Conditional Approval | AMIR NAZARIAN |
| Final | 5/2/2024 | Conditional Approval | AMIR NAZARIAN |
| Service/Power Release | 5/2/2024 | Approved | AMIR NAZARIAN |
| Final | 5/6/2024 | OK to Issue CofO | AMIR NAZARIAN |