12303 W ERWIN ST 91606

Certificate Information: 12303 W ERWIN ST 91606

Application / Permit
21010-10000-02156
Plan Check / Job No.
B21LA08093
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. PROPOSED 2 STORY DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 6/24/2024
Issuing Office
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 CRYSTEL MAALOUF
Corrections Issued 6/22/2021 CRYSTEL MAALOUF
Quality Review Completed 7/1/2021 WING SUEN
Applicant returned to address corrections 5/9/2022 CRYSTEL MAALOUF
Plan Check Approved 6/13/2022 CRYSTEL MAALOUF
Plan Check Approved 1/4/2024 CRYSTEL MAALOUF
Issued 6/24/2024 APPLICANT
CofO in Progress 4/8/2026 RAUL OLAGI
Permit Finaled 4/16/2026 RUBEN SALAS
CofO Issued 4/16/2026 RUBEN SALAS
Permit Finaled 4/16/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/9/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/9/2021 CARLOS AGUILERA
Sewer availability Cleared 9/9/2021 CARLOS AGUILERA
Low Impact Development Cleared 1/24/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 1/25/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/19/2022 LAURINDA MEADE

Contact Information

Contractor Hammerhead Construction; Lic. No.: 868943-B 5315 BUFFINGTON RD      EL MONTE, CA 91732
Engineer Santos,, Michael Fernandez; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/21/2024 Approved SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 10/17/2024 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 10/22/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/14/2025 No Access for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/14/2025 No Access for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 No Access for Inspection GAREN HAYRAPETYAN
Gas Test 4/14/2025 No Access for Inspection GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/14/2025 No Access for Inspection GAREN HAYRAPETYAN
MERV13>=Rough 4/14/2025 No Access for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 4/14/2025 No Access for Inspection GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 4/14/2025 No Access for Inspection GAREN HAYRAPETYAN
Wood Frame 4/14/2025 No Access for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/16/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Gas Test 4/16/2025 No Access for Inspection GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/16/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 4/16/2025 Corrections Issued GAREN HAYRAPETYAN
Wood Frame 4/16/2025 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 4/21/2025 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/21/2025 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Gas Test 4/21/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 4/21/2025 Not Ready for Inspection JOAQUIN GREENOUGH
MERV13>=Rough 4/21/2025 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 4/21/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 4/21/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 4/21/2025 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/24/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Approved GAREN HAYRAPETYAN
Gas Test 4/24/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/24/2025 Corrections Issued GAREN HAYRAPETYAN
MERV13>=Rough 4/24/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 4/24/2025 Approved GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 4/24/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 6/25/2025 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/10/2025 Corrections Issued RAUL OLAGI
HVAC-Rough 7/10/2025 Corrections Issued RAUL OLAGI
MERV13>=Rough 7/10/2025 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/25/2025 Approved OGANES TARAKHCHYAN
Insulation 9/2/2025 Corrections Issued LOUIS ESCOTO
Drywall Nailing 9/11/2025 Corrections Issued OGANES TARAKHCHYAN
Drywall Nailing 9/16/2025 Approved LOUIS ESCOTO
Insulation 9/16/2025 Approved LOUIS ESCOTO
Shower Pan 10/9/2025 Approved OGANES TARAKHCHYAN
Gas Test 2/4/2026 Not Ready for Inspection MICHAEL CORTEZ
Final 2/19/2026 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 2/19/2026 Approved KIRK SANDERS
Gas Test 2/19/2026 Approved KIRK SANDERS
MERV13>=Final 2/19/2026 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 2/19/2026 SGSOV Approved KIRK SANDERS
Service/Power Release 2/19/2026 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 2/19/2026 Not Ready for Inspection KIRK SANDERS
Final 3/5/2026 Not Ready for Inspection WAYNE REGESTER
MERV13>=Final 3/5/2026 Not Ready for Inspection WAYNE REGESTER
Service/Power Release 3/5/2026 Approved WAYNE REGESTER
Smoke Detectors 3/5/2026 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 3/16/2026 Approved WAYNE REGESTER
Final 3/16/2026 OK to Issue CofO WAYNE REGESTER
Green Building Final 3/16/2026 Approved WAYNE REGESTER
HVAC-Final 3/16/2026 Approved WAYNE REGESTER
MERV13>=Final 3/16/2026 Approved WAYNE REGESTER
PLUMBING-Final 3/16/2026 Approved WAYNE REGESTER
Smoke Detectors 3/16/2026 Approved WAYNE REGESTER