121-121 1/2 E ADAMS BLVD 90011
Certificate Information: 121-121 1/2 E ADAMS BLVD 90011
- Application / Permit
- 21010-10000-02146
- Plan Check / Job No.
- B21LA08068
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 29.5' X 40.5' (2160.5 SF) 2-STORY DUPLEX AT FRONT. 1 OF 2
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Current Status
- CofO Issued on 9/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | VIVIAN LAO |
| Corrections Issued | 5/21/2021 | VIVIAN LAO |
| Quality Review Completed | 5/26/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/18/2021 | VIVIAN LAO |
| Plan Check Approved | 10/28/2021 | VIVIAN LAO |
| Issued | 11/5/2021 | APPLICANT |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
| CofO in Progress | 8/22/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
| CofO Issued | 9/11/2022 | DEROLD HAUFF |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 8/17/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/17/2021 | CECILIO NAVARRO |
| Highway dedication | Cleared | 9/3/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 9/16/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 9/17/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 10/1/2021 | KURT CORRAL |
Contact Information
| Contractor | Rios William A; Lic. No.: 866335-B | P O BOX 1061 DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 11/19/2021 | Partial Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/19/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/23/2021 | Approved | JOAQUIN GREENOUGH |
| METHANE-Barrier | 11/23/2021 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 11/23/2021 | Approved | JOAQUIN GREENOUGH |
| Special/Order Compliance | 11/23/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Partial Approval | HORACE FULTZ |
| Deputy Wood Construction | 1/4/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 1/26/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 1/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 1/26/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 1/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 1/26/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/26/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 1/26/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/1/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 2/1/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 2/1/2022 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 2/1/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 2/9/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/11/2022 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 2/14/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 2/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Final | 8/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 8/4/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 8/4/2022 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/4/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 8/17/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Service/Power Release | 8/22/2022 | Approved | JOAQUIN GREENOUGH |