121-121 1/2 E ADAMS BLVD 90011

Certificate Information: 121-121 1/2 E ADAMS BLVD 90011

Application / Permit
21010-10000-02146
Plan Check / Job No.
B21LA08068
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 29.5' X 40.5' (2160.5 SF) 2-STORY DUPLEX AT FRONT. 1 OF 2
Permit Issued
Issued on 11/5/2021
Issuing Office
Current Status
CofO Issued on 9/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 VIVIAN LAO
Corrections Issued 5/21/2021 VIVIAN LAO
Quality Review Completed 5/26/2021 MICHAEL PEREZ
Applicant returned to address corrections 10/18/2021 VIVIAN LAO
Plan Check Approved 10/28/2021 VIVIAN LAO
Issued 11/5/2021 APPLICANT
Building Plans Picked Up 11/8/2021 APPLICANT
CofO in Progress 8/22/2022 JOAQUIN GREENOUGH
Permit Finaled 9/11/2022 DEROLD HAUFF
CofO Issued 9/11/2022 DEROLD HAUFF
Permit Finaled 9/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/22/2021 CECILIO NAVARRO
Address approval Cleared 8/17/2021 CECILIO NAVARRO
Sewer availability Cleared 8/17/2021 CECILIO NAVARRO
Highway dedication Cleared 9/3/2021 CECILIO NAVARRO
Low Impact Development Cleared 9/16/2021 KHAING AYE
Roof/Waste drainage to street Cleared 9/17/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 10/1/2021 KURT CORRAL

Contact Information

Contractor Rios William A; Lic. No.: 866335-B P O BOX 1061      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 11/19/2021 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 11/19/2021 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/23/2021 Approved JOAQUIN GREENOUGH
METHANE-Barrier 11/23/2021 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 11/23/2021 Approved JOAQUIN GREENOUGH
Special/Order Compliance 11/23/2021 Partial Inspection SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Partial Approval HORACE FULTZ
Deputy Wood Construction 1/4/2022 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/26/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 1/26/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 1/26/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 1/26/2022 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 1/26/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Rough 1/26/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 1/26/2022 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 1/26/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/1/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 2/1/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 2/1/2022 Approved JOAQUIN GREENOUGH
Wood Frame 2/1/2022 Approved JOAQUIN GREENOUGH
Insulation 2/9/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 2/11/2022 Off-Hour Fees Due
Interior/Exterior Lathing 2/14/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 2/17/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Not Ready JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Final 8/4/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 8/4/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/4/2022 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 8/4/2022 Approved JOAQUIN GREENOUGH
Smoke Detectors 8/4/2022 Approved JOAQUIN GREENOUGH
Final 8/17/2022 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 8/22/2022 Approved JOAQUIN GREENOUGH