432-434 E 59TH PL 90003

Certificate Information: 432-434 E 59TH PL 90003

Application / Permit
21010-10000-02122
Plan Check / Job No.
B21LA07993
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR
Permit Issued
Issued on 9/21/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 BIDYUT RATH
Corrections Issued 6/7/2021 BIDYUT RATH
Quality Review Completed 6/10/2021 HANS SANTIAGO
Applicant returned to address corrections 9/7/2021 BIDYUT RATH
Applicant returned to address corrections 9/9/2021 BIDYUT RATH
Plan Check Approved 9/14/2021 BIDYUT RATH
Issued 9/21/2021 APPLICANT
Building Plans Picked Up 9/23/2021 APPLICANT
CofO in Progress 3/7/2022 JOAQUIN GREENOUGH
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/23/2021 STEVE MELGAR
Permit Cleared 6/23/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/1/2021 STEVE MELGAR
Sewer availability Cleared 7/1/2021 STEVE MELGAR
Highway dedication Cleared 7/13/2021 THOMAS LANG
Hydrant and Access approval Cleared 7/20/2021 ROBERT DUFF
Low Impact Development Cleared 8/3/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/10/2021 CELINA MORENO
Trees in Parkway Cleared 8/24/2021 JOHN KIM

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/15/2021 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 10/29/2021 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 10/29/2021 Approved ALEJANDRO DE ARTOLA
Insulation 11/1/2021 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/12/2021 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Approved SABAS ALONSO
HVAC-Rough 12/14/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 12/14/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/16/2021 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/16/2021 Approved JOAQUIN GREENOUGH
Green Building Rough 12/16/2021 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 12/16/2021 Approved JOAQUIN GREENOUGH
Insulation 12/17/2021 Approved JOAQUIN GREENOUGH
Drywall Nailing 12/28/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 12/28/2021 Approved ADAM ESCOTO
ELECTRICAL-Final 2/3/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 3/1/2022 Approved JOAQUIN GREENOUGH
Final 3/1/2022 Partial Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/1/2022 Approved JOAQUIN GREENOUGH
HVAC-Final 3/1/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Final 3/1/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 3/1/2022 Approved JOAQUIN GREENOUGH
Smoke Detectors 3/1/2022 Approved JOAQUIN GREENOUGH
Final 3/2/2022 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 3/2/2022 Approved JOAQUIN GREENOUGH