2344 E FERNLEAF ST 90031

Certificate Information: 2344 E FERNLEAF ST 90031

Application / Permit
21010-10000-02114
Plan Check / Job No.
B21LA07934
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New State Approved FBH detached ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 1/5/2022
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 5/4/2021 RICARDO RAMIREZ
Corrections Issued 5/4/2021 RICARDO RAMIREZ
Plan Check Approved 1/3/2022 CHRISTOPHER KOMANCHECK
Issued 1/5/2022 APPLICANT
Building Plans Picked Up 1/7/2022 APPLICANT
CofO in Progress 4/22/2022 RUBEN SALAS
Permit Finaled 4/28/2022 DEROLD HAUFF
CofO Issued 4/28/2022 DEROLD HAUFF
Permit Finaled 4/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/2/2021 RENZ SORIANO
Hydrant and Access approval Cleared 7/15/2021 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 7/19/2021 RENZ SORIANO
Sewer availability Cleared 7/19/2021 RENZ SORIANO
Low Impact Development Cleared 10/21/2021 CHRIS PARK
ZI Cleared 10/21/2021 RICHARD REASER
Roof/Waste drainage to street Cleared 10/26/2021 STEVE MELGAR
Construction near power lines Cleared 10/28/2021 WALTER RAMIREZ

Contact Information

Contractor Cover Technologies Inc; Lic. No.: 1039029-B 1219 W 135TH STREET      GARDENA, CA 90247
Engineer Nielsen,, Gregory Michael Wat; Lic. No.: S6653 900 WILSHIRE BLVD 19TH FLOOR      LOS ANGELES, CA 90017

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/28/2022 Approved RAUL BARAJAS
Underground Mechanical 1/28/2022 Approved RAUL BARAJAS
Footing/Foundation/Slab 2/8/2022 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 2/10/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 2/16/2022 Off-Hour Fees Due
Gas Test 2/16/2022 Off-Hour Fees Due
Gas Test 2/16/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 2/16/2022 Off-Hour Fees Due
Underground Mechanical 2/16/2022 Approved THOMAS LOGRASSO
Underground Mechanical 2/16/2022 Off-Hour Fees Due
Footing/Foundation/Slab 2/23/2022 Partial Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 2/28/2022 Conditional Approval RUBEN SALAS
BUILDING-Rough-Frame 3/25/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 3/25/2022 Off-Hour Fees Due
Final 3/25/2022 Corrections Issued THOMAS LOGRASSO
Final 3/25/2022 Off-Hour Fees Due
Footing/Foundation/Slab 3/25/2022 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 3/25/2022 Off-Hour Fees Due
Green Building Final 3/25/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 3/25/2022 Off-Hour Fees Due
Green Building Rough 3/25/2022 Approved THOMAS LOGRASSO
Green Building Rough 3/25/2022 Off-Hour Fees Due
MERV13>=Final 3/25/2022 Off-Hour Fees Due
MERV13>=Rough 3/25/2022 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 3/25/2022 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 3/25/2022 Not Ready for Inspection THOMAS LOGRASSO
Service/Power Release 3/25/2022 Off-Hour Fees Due
Smoke Detectors 3/25/2022 Approved THOMAS LOGRASSO
Smoke Detectors 3/25/2022 Off-Hour Fees Due
Verify Sprinkler Sign Off 3/25/2022 Off-Hour Fees Due
Final 4/1/2022 Not Ready for Inspection RUBEN SALAS
Green Building Final 4/1/2022 Not Ready for Inspection RUBEN SALAS
Service/Power Release 4/1/2022 Not Ready for Inspection RUBEN SALAS
Final 4/6/2022 Conditional Approval RUBEN SALAS
Green Building Final 4/6/2022 Approved RUBEN SALAS
Service/Power Release 4/6/2022 Approved RUBEN SALAS