3928 S ARLINGTON AVE 90008

Certificate Information: 3928 S ARLINGTON AVE 90008

Application / Permit
21010-10000-02097
Plan Check / Job No.
B21LA07853
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New two-story ADU.
Permit Issued
Issued on 7/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 RODOLFO ARIAS
Corrections Issued 7/8/2021 RODOLFO ARIAS
Quality Review Completed 7/12/2021 EUGENE BARBEAU
Applicant returned to address corrections 5/17/2022 RODOLFO ARIAS
Applicant returned to address corrections 6/9/2022 RODOLFO ARIAS
Plan Check Approved 6/16/2022 RODOLFO ARIAS
Issued 7/13/2022 APPLICANT
CofO in Progress 6/9/2023 ANTHONY EGSON
Permit Finaled 2/1/2024 DEROLD HAUFF
CofO Issued 2/1/2024 DEROLD HAUFF
Permit Finaled 2/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/23/2021 JEANIE LAM
Permit Cleared 11/23/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/24/2022 JEANIE LAM
Sewer availability Cleared 1/24/2022 JEANIE LAM
Hydrant and Access approval Cleared 3/5/2022 CINDY JOSSELYN
Low Impact Development Cleared 3/9/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 3/10/2022 AMAAN MALIK
Miscellaneous Cleared 3/30/2022 ALBERT TAM

Contact Information

Contractor Golden Construction Group Llc; Lic. No.: 1078364-B 16814 CITRONIA STREET      NORTHRIDGE, CA 91343
Engineer Moreno,, Hector M; Lic. No.: C66015 1430 E COOLEY DR SUITE 120      COLTON, CA 92324

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/3/2022 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 8/8/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 8/8/2022 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 8/12/2022 Approved ANTHONY EGSON
Sewer 9/28/2022 Corrections Issued ANTHONY EGSON
Sewer 10/3/2022 Approved ANTHONY EGSON
Deputy Wood Construction 10/12/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Corrections Issued ANTHONY EGSON
Insulation 10/12/2022 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 10/18/2022 Not Ready for Inspection ANTHONY EGSON
Deputy Drilled-In Anchors 10/18/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Approved ANTHONY EGSON
Green Building Rough 10/18/2022 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 11/3/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 11/3/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 11/3/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 11/3/2022 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 11/3/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 11/14/2022 Corrections Issued ANTHONY EGSON
HVAC-Rough 11/14/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 11/14/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 11/18/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Approved ANTHONY EGSON
HVAC-Rough 11/18/2022 Approved ANTHONY EGSON
PLUMBING-Rough 11/18/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 11/23/2022 Approved ANTHONY EGSON
Insulation 11/28/2022 Corrections Issued ANTHONY EGSON
Insulation 12/2/2022 Approved ANTHONY EGSON
Drywall Nailing 12/7/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 12/7/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/7/2022 Approved ALIZAH MAYAGOITIA
Underground Mechanical 12/7/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/20/2023 Not Ready for Inspection ANTHONY EGSON
Final 1/20/2023 Corrections Issued ANTHONY EGSON
Green Building Final 1/20/2023 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Not Ready ANTHONY EGSON
Service/Power Release 1/20/2023 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 1/20/2023 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 1/26/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 1/26/2023 Corrections Issued ANTHONY EGSON
Final 1/26/2023 Corrections Issued ANTHONY EGSON
HVAC-Final 1/26/2023 Approved ANTHONY EGSON
PLUMBING-Final 1/26/2023 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/26/2023 SGSOV Approved ANTHONY EGSON
Service/Power Release 1/26/2023 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 1/26/2023 Approved ANTHONY EGSON
Verify Sprinkler Sign Off 1/26/2023 Approved ANTHONY EGSON
Final 2/6/2023 Corrections Issued STUART CHAPMAN
Service/Power Release 2/6/2023 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 6/8/2023 Approved ANTHONY EGSON
Final 6/8/2023 OK to Issue CofO ANTHONY EGSON
PLUMBING-Final 6/8/2023 Approved ANTHONY EGSON
Service/Power Release 6/8/2023 Approved ANTHONY EGSON