3928 S ARLINGTON AVE 90008
Certificate Information: 3928 S ARLINGTON AVE 90008
- Application / Permit
- 21010-10000-02097
- Plan Check / Job No.
- B21LA07853
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New two-story ADU.
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | RODOLFO ARIAS |
| Corrections Issued | 7/8/2021 | RODOLFO ARIAS |
| Quality Review Completed | 7/12/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 5/17/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/9/2022 | RODOLFO ARIAS |
| Plan Check Approved | 6/16/2022 | RODOLFO ARIAS |
| Issued | 7/13/2022 | APPLICANT |
| CofO in Progress | 6/9/2023 | ANTHONY EGSON |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
| CofO Issued | 2/1/2024 | DEROLD HAUFF |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2021 | JEANIE LAM |
| Permit | Cleared | 11/23/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | JEANIE LAM |
| Sewer availability | Cleared | 1/24/2022 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 3/5/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 3/9/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/10/2022 | AMAAN MALIK |
| Miscellaneous | Cleared | 3/30/2022 | ALBERT TAM |
Contact Information
| Contractor | Golden Construction Group Llc; Lic. No.: 1078364-B | 16814 CITRONIA STREET NORTHRIDGE, CA 91343 |
| Engineer | Moreno,, Hector M; Lic. No.: C66015 | 1430 E COOLEY DR SUITE 120 COLTON, CA 92324 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/3/2022 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 8/8/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/8/2022 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/12/2022 | Approved | ANTHONY EGSON |
| Sewer | 9/28/2022 | Corrections Issued | ANTHONY EGSON |
| Sewer | 10/3/2022 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 10/12/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Corrections Issued | ANTHONY EGSON |
| Insulation | 10/12/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/18/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 10/18/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/18/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/3/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/3/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 11/3/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 11/3/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 11/3/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/14/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 11/14/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 11/14/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/18/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 11/18/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/18/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/23/2022 | Approved | ANTHONY EGSON |
| Insulation | 11/28/2022 | Corrections Issued | ANTHONY EGSON |
| Insulation | 12/2/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 12/7/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 12/7/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/7/2022 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 12/7/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 1/20/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/20/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/20/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 1/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 1/20/2023 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/26/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 1/26/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 1/26/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 1/26/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 1/26/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 1/26/2023 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 1/26/2023 | Approved | ANTHONY EGSON |
| Final | 2/6/2023 | Corrections Issued | STUART CHAPMAN |
| Service/Power Release | 2/6/2023 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 6/8/2023 | Approved | ANTHONY EGSON |
| Final | 6/8/2023 | OK to Issue CofO | ANTHONY EGSON |
| PLUMBING-Final | 6/8/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 6/8/2023 | Approved | ANTHONY EGSON |