6500 S AVALON BLVD 90003

Certificate Information: 6500 S AVALON BLVD 90003

Application / Permit
21010-10000-02095
Plan Check / Job No.
B21LA07848
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Household Goods Storage
Work Description
NEW 3-STORY TYPE II-B HOUSEHOLD GOOD SELF-STORAGE BUILDING PER ZA-2019-5588-CU-CPIOA-SPR
Permit Issued
Issued on 4/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Building Plans Picked Up 5/19/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 GARO TELMI
Corrections Issued 6/2/2021 GARO TELMI
Quality Review Completed 6/3/2021 KEN GILL
Green Plans Picked Up 8/27/2021 APPLICANT
Applicant returned to address corrections 9/2/2021 GARO TELMI
Applicant returned to address corrections 9/16/2021 GARO TELMI
Applicant returned to address corrections 10/21/2021 GARO TELMI
Applicant returned to address corrections 1/27/2022 GARO TELMI
Plan Check Approved 4/27/2022 GARO TELMI
No Progress 4/27/2022 GARO TELMI
Plan Check Approved 4/27/2022 GARO TELMI
Plan Check Approved 4/27/2022 GARO TELMI
Issued 4/28/2022 APPLICANT
CofO in Progress 4/26/2024 JAMES POWERS
Permit Finaled 4/26/2024 ERNESTO CORRAL
CofO Issued 4/26/2024 ERNESTO CORRAL
Permit Finaled 4/26/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 9/8/2021 WALLIE JONG
Community Plan Implem. Overlay Cleared 9/8/2021 WALLIE JONG
Permit Cleared 9/8/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/15/2021 WALLIE JONG
Hydrant and Access approval Cleared 9/19/2021 ROBERT DUFF
Green Code Cleared 9/22/2021 GARO TELMI
Sewer availability Cleared 9/22/2021 WALLIE JONG
Historic Resource Verification Cleared 10/8/2021 MICAELA TORRES-GIL
Community Plan Implem. Overlay Cleared 10/13/2021 EDUARDO HERMOSO
Internal circulation Cleared 10/13/2021 EDUARDO HERMOSO
Highway dedication Cleared 10/20/2021 WALLIE JONG
Bicycle Parking Cleared 10/26/2021 JEREMY CHOK
Miscellaneous Cleared 11/9/2021 ALBERT TAM
Community Plan Implem. Overlay Cleared 12/22/2021 RIDWAN HARDY
Construction near power lines Cleared 12/22/2021 RIDWAN HARDY
Construction within easement Cleared 12/22/2021 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 2/8/2022 ADRIAN SANCHEZ
Low Impact Development Cleared 2/11/2022 AMMAR ELTAWIL
Trees in Parkway Cleared 2/23/2022 ADALBERTO VERA
Roof/Waste drainage to street Cleared 3/22/2022 WALLIE JONG
DAS Clearance Cleared 3/24/2022 SHINE LIN
CPC Cleared 3/29/2022 ANNA VIDAL
Prkng lot landscape/Water mgmt Cleared 3/29/2022 ANNA VIDAL
Site Plan review Cleared 3/29/2022 ANNA VIDAL
ZA Case Cleared 3/29/2022 ANNA VIDAL
Community Plan Implem. Overlay Cleared 4/5/2022 HELEN JADALI
Work Adjacent to Public Way Cleared 4/14/2022 JOSE RODRIGUEZ
Redevelopment Project Area Cleared 4/18/2022 GRACIELA ACOSTA
Excavation more than 5-ft deep Cleared 4/22/2022 CALOSHA APPROVED
Building over 36-ft Cleared 4/27/2022 CALOSHA APPROVED

Contact Information

Architect Vakili,, Shabnam; Lic. No.: C26298 KSP STUDIO   23 ORCHARD STE 200    LAKE FOREST, CA 92630
Contractor Padelford A J & Son Inc; Lic. No.: 222840-B P O BOX 185      ARTESIA, CA 907020185
Engineer Gray,, David R; Lic. No.: L5239 601 EAST DAILY DR STE 225      CAMARILLO, CA 93010
Engineer Huber,, Benjamin Zekl; Lic. No.: C88412 1923 BLUEBELL DR      LIVERMORE, CA 94551
Engineer Kling,, Henry Floyd; Lic. No.: GE2205 11 PLYMOUTH      IRVINE, CA 92620
Engineer Salter,, David R; Lic. No.: C69911 3445 CEDAR ST      SANTA YNEZ, CA 93460
Engineer Shakerin,, Kayvon; Lic. No.: C46202 23 ORCHARD ROAD STE 200      LAKE FOREST, CA 92630
Geologist Blake,, Jeffrey Paul; Lic. No.: EG2248 1857 PALISADES DR      CARLSBAD, CA 92008

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 10/13/2022 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 10/13/2022 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 10/14/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 10/17/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/26/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/26/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/26/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/26/2022 Partial Approval JAMES POWERS
Reinforced Masonry Frame 10/26/2022 Partial Approval JAMES POWERS
Masonry Wall/Backfill 11/1/2022 Partial Inspection GREGORY POMISH
Deputy Reinf. Masonry 11/2/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/7/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/10/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 11/10/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/15/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/17/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/18/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/22/2022 Partial Approval JAMES POWERS
Reinforced Masonry Frame 11/22/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/1/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/2/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/6/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/7/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/8/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/9/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 2/10/2023 Partial Approval ALAN MORELOS
Structural Steel Frame 2/10/2023 Partial Approval ALAN MORELOS
Deputy Reinf. Concrete 2/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/14/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 2/15/2023 Partial Approval JAMES POWERS
Structural Steel Frame 2/15/2023 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/16/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/17/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/17/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 3/13/2023 Conditional Approval MICHAEL ROSENBERG
Structural Steel Frame 3/16/2023 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 4/14/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 4/18/2023 Partial Approval ALAN MORELOS
Light Gage Steel Frame 4/19/2023 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 4/20/2023 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 4/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 4/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/2/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/2/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/3/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/4/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/4/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 5/5/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 5/8/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/17/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/17/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/17/2023 Partial Approval JAMES POWERS
Structural Steel Frame 5/17/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 5/30/2023 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 6/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 6/13/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 6/13/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/21/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/21/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/23/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 6/23/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 6/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 6/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 7/3/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 7/3/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 7/26/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/3/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/4/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/7/2023 Partial Approval JAMES POWERS
Insulation 8/8/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/9/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/10/2023 Partial Approval JAMES POWERS
Drywall Nailing 8/10/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/11/2023 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/16/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/29/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/28/2023 Partial Approval JAMES POWERS
Drywall Nailing 10/20/2023 Partial Approval LARRY ARNICK
T-Bar Ceiling 10/24/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 10/30/2023 Approved LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/1/2023 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/3/2023 Partial Approval LARRY ARNICK
Deputy Steel/Welding 12/8/2023 Partial Approval JAMES POWERS
Special/Order Compliance 12/29/2023 Not Ready for Inspection JAMES POWERS
Final 3/18/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 3/18/2024 Approved JAMES POWERS
Green Building Final 3/18/2024 Approved JAMES POWERS
Green Building Rough 3/18/2024 Approved JAMES POWERS
Reinforced Masonry Frame 3/18/2024 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV No Gas JAMES POWERS
Smoke Detectors 3/18/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 3/18/2024 Not Ready for Inspection JAMES POWERS
Final 4/18/2024 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 4/18/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/18/2024 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 4/26/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/26/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/26/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/26/2024 Partial Approval JAMES POWERS
Final 4/26/2024 OK to Issue CofO JAMES POWERS
Reinforced Masonry Frame 4/26/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 4/26/2024 Approved JAMES POWERS