2313 N ECHO PARK AVE 90026

Certificate Information: 2313 N ECHO PARK AVE 90026

Application / Permit
21010-10000-02094
Plan Check / Job No.
B21LA07841
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW ACCESSORY LIVING QUATER, SINGLE STORY 259SQFT 1 OF 3
Permit Issued
Issued on 6/24/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 SERGIO GUTIERREZ
Corrections Issued 6/2/2021 SERGIO GUTIERREZ
Quality Review Completed 6/9/2021 FARUK SEZER
Building Plans Picked Up 6/14/2021 APPLICANT
Applicant returned to address corrections 10/29/2021 SERGIO GUTIERREZ
Applicant returned to address corrections 12/17/2021 SERGIO GUTIERREZ
Plan Check Approved 1/11/2022 SERGIO GUTIERREZ
Issued 6/24/2022 APPLICANT
CofO in Progress 6/4/2024 HAMIK HARTOUNIAN
Permit Finaled 6/6/2024 DEROLD HAUFF
CofO Issued 6/6/2024 DEROLD HAUFF
Permit Finaled 6/6/2024 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 12/17/2021 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 12/17/2021 SERGIO GUTIERREZ
Highway dedication Cleared 12/27/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 12/27/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/4/2022 CELINA MORENO
Sewer availability Cleared 1/5/2022 CELINA MORENO

Contact Information

Contractor Alexander Building Co; Lic. No.: 980164-B 1072 HOLLYGROVE LN      ALTADENA, CA 91001
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/1/2023 Partial Inspection THOMAS LOGRASSO
Deputy Reinf. Concrete 4/28/2023 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 5/5/2023 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 6/6/2023 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Partial Approval THOMAS LOGRASSO
Insulation 6/26/2023 Partial Approval THOMAS LOGRASSO
Sewer 6/26/2023 Approved THOMAS LOGRASSO
Underground Mechanical 6/26/2023 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Partial Approval THOMAS LOGRASSO
Deputy Steel/Welding 8/7/2023 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 9/7/2023 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 9/14/2023 Partial Approval THOMAS LOGRASSO
HVAC-Rough 10/3/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/3/2023 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 10/3/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/6/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 10/6/2023 Approved THOMAS LOGRASSO
Insulation 10/12/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/17/2023 Approved THOMAS LOGRASSO
Drywall Nailing 10/17/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 11/17/2023 Approved THOMAS LOGRASSO
Shower Pan 11/17/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 4/19/2024 Approved SCOTT FINNILA
Final 4/19/2024 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 4/19/2024 Approved SCOTT FINNILA
Green Building Final 4/19/2024 Approved SCOTT FINNILA
Green Building Rough 4/19/2024 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 4/19/2024 SGSOV Approved SCOTT FINNILA
Service/Power Release 4/19/2024 Approved SCOTT FINNILA
Smoke Detectors 4/19/2024 Corrections Issued SCOTT FINNILA
Final 5/15/2024 Corrections Issued HAMIK HARTOUNIAN
Smoke Detectors 5/15/2024 Approved HAMIK HARTOUNIAN
Final 5/21/2024 OK to Issue CofO HAMIK HARTOUNIAN