1825 S GAFFEY ST 90731
Certificate Information: 1825 S GAFFEY ST 90731
- Application / Permit
- 21010-10000-02087
- Plan Check / Job No.
- B21LA07817
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING (FRONT BLDG) 1 OF 2
- Permit Issued
- Issued on 6/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | VARAND SARKISIAN |
| Corrections Issued | 5/17/2021 | VARAND SARKISIAN |
| Quality Review Completed | 5/19/2021 | HANS SANTIAGO |
| Building Plans Picked Up | 5/20/2021 | APPLICANT |
| Applicant returned to address corrections | 4/21/2022 | VARAND SARKISIAN |
| Plan Check Approved | 5/18/2022 | VARAND SARKISIAN |
| Issued | 6/22/2022 | APPLICANT |
| CofO in Progress | 12/4/2023 | ANSON MAGLASANG |
| Permit Finaled | 12/4/2023 | ANSON MAGLASANG |
| CofO Issued | 12/4/2023 | ANSON MAGLASANG |
| Permit Finaled | 12/4/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2021 | ERIK BEASLEY |
| Permit | Cleared | 5/21/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 6/4/2021 | ERIK BEASLEY |
| Frnt yard landscape/Water mgmt | Cleared | 6/17/2021 | DANIEL CORONADO |
| Trees in Parkway | Cleared | 7/15/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/8/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/6/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 12/2/2021 | WALTER RAMIREZ |
| Highway dedication | Cleared | 4/26/2022 | ERIK BEASLEY |
| GPI Written Notices | Cleared | 5/4/2022 | VARAND SARKISIAN |
| Grading Pre-Inspection | Cleared | 5/4/2022 | VARAND SARKISIAN |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Mchantaf,, Kamal Beshara; Lic. No.: C51050 | 23315 SARATOGA SPRINGS PL MURRIETA, CA 92562 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/30/2022 | Partial Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 9/7/2022 | Approved | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 2/1/2023 | Not Ready for Inspection | JULIAN AMAYA |
| ELECTRICAL-Rough | 2/1/2023 | Partial Inspection | JULIAN AMAYA |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | JULIAN AMAYA |
| HVAC-Rough | 2/1/2023 | Partial Inspection | JULIAN AMAYA |
| PLUMBING-Rough | 2/1/2023 | Partial Inspection | JULIAN AMAYA |
| Rough-Elec/Plmb/HVAC | 2/1/2023 | Corrections Issued | JULIAN AMAYA |
| Verify Sprinkler Sign Off | 2/1/2023 | Not Ready for Inspection | JULIAN AMAYA |
| ELECTRICAL-Rough | 2/6/2023 | Approved | ANSON MAGLASANG |
| HVAC-Rough | 2/6/2023 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 2/6/2023 | Approved | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 2/6/2023 | Approved | ANSON MAGLASANG |
| Insulation | 2/21/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 2/21/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 3/14/2023 | Approved | ANSON MAGLASANG |
| Green Building Rough | 3/14/2023 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 4/25/2023 | Partial Approval | ANSON MAGLASANG |
| Shower Pan | 4/25/2023 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 10/19/2023 | Approved | JAMES CHAVEZ |
| HVAC-Final | 10/19/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 10/19/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 12/1/2023 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 12/1/2023 | Approved | ANSON MAGLASANG |
| Final | 12/1/2023 | OK to Issue CofO | ANSON MAGLASANG |
| Green Building Final | 12/1/2023 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | ANSON MAGLASANG |
| Service/Power Release | 12/1/2023 | Approved | ANSON MAGLASANG |
| Smoke Detectors | 12/1/2023 | Approved | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 12/1/2023 | Approved | ANSON MAGLASANG |