10627 S BROADWAY 90003

Certificate Information: 10627 S BROADWAY 90003

Application / Permit
21010-10000-02084
Plan Check / Job No.
B21LA07784
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 2/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 DANIEL YIP
Corrections Issued 5/20/2021 DANIEL YIP
Quality Review Completed 5/21/2021 JASON HEALEY
Applicant returned to address corrections 10/14/2021 DANIEL YIP
Plan Check Approved 11/29/2021 DANIEL YIP
Issued 1/12/2022 APPLICANT
Building Plans Picked Up 1/14/2022 APPLICANT
CofO in Progress 1/24/2023 JAMES CHAVEZ
CofO Issued 2/1/2023 ANSON MAGLASANG
Permit Finaled 2/1/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 6/10/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/10/2021 STEVE MELGAR
Sewer availability Cleared 6/22/2021 STEVE MELGAR
Hydrant and Access approval Cleared 7/26/2021 MATTHEW CRAIG
Low Impact Development Cleared 9/29/2021 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/4/2021 STEVE MELGAR
Frnt yard landscape/Water mgmt Cleared 11/1/2021 LOUIS ORTEGA

Contact Information

Contractor F S Z Bros General Contractors Inc; Lic. No.: 794097-B 9036 IMPERIAL HWY      DOWNEY, CA 90242

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/28/2022 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 2/3/2022 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 2/7/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/9/2022 Corrections Issued ALIZAH MAYAGOITIA
Verify Rec and Parks Fee Memo 5/9/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 5/31/2022 Approved JOHN KLARIN
PLUMBING-Rough 5/31/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 6/14/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Corrections Issued JOHN KLARIN
HVAC-Rough 6/14/2022 Approved JOHN KLARIN
PLUMBING-Rough 6/14/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 6/15/2022 Not Ready for Inspection JOHN KLARIN
Green Building Rough 6/15/2022 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 6/15/2022 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 6/15/2022 Not Ready for Inspection JOHN KLARIN
Wood Frame 6/22/2022 Approved JOHN KLARIN
Green Building Rough 7/11/2022 Approved JOHN KLARIN
Insulation 7/11/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 7/11/2022 Approved JOHN KLARIN
Drywall Nailing 7/18/2022 Not Ready for Inspection JOHN KLARIN
Drywall Nailing 7/20/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/21/2022 Partial Approval JOHN KLARIN
Final 10/21/2022 Corrections Issued JOHN KLARIN
Green Building Final 10/21/2022 Corrections Issued JOHN KLARIN
MERV13>=Final 10/21/2022 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 10/21/2022 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 10/21/2022 SGSOV Not Ready JOHN KLARIN
Service/Power Release 10/21/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 10/21/2022 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 10/21/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 12/20/2022 Approved JAMES CHAVEZ
Gas Test 12/20/2022 Approved JAMES CHAVEZ
HVAC-Final 12/20/2022 Approved JAMES CHAVEZ
PLUMBING-Final 12/20/2022 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 1/17/2023 Approved JULIAN AMAYA
ELECTRICAL-Final 1/17/2023 Approved JULIAN AMAYA
Final 1/17/2023 Corrections Issued JULIAN AMAYA
Green Building Final 1/17/2023 Not Ready for Inspection JULIAN AMAYA
HVAC-Final 1/17/2023 Approved JULIAN AMAYA
MERV13>=Final 1/17/2023 Approved JULIAN AMAYA
MERV13>=Rough 1/17/2023 Approved JULIAN AMAYA
PLUMBING-Final 1/17/2023 Approved JULIAN AMAYA
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Approved JULIAN AMAYA
Service/Power Release 1/17/2023 Not Ready for Inspection JULIAN AMAYA
Smoke Detectors 1/17/2023 Approved JULIAN AMAYA
Verify Sprinkler Sign Off 1/17/2023 Approved JULIAN AMAYA
ELECTRICAL-Final 1/18/2023 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 1/18/2023 Off-Hour Fees Due
HVAC-Final 1/18/2023 Off-Hour Fees Due
PLUMBING-Final 1/18/2023 Off-Hour Fees Due
ELECTRICAL-Final 1/19/2023 Approved JAMES CHAVEZ
Final 1/19/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Final 1/19/2023 Approved JAMES CHAVEZ
PLUMBING-Final 1/19/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 1/23/2023 Approved JAMES CHAVEZ
Final 1/23/2023 OK to Issue CofO JAMES CHAVEZ
Green Building Final 1/23/2023 Approved JAMES CHAVEZ
HVAC-Final 1/23/2023 Approved JAMES CHAVEZ
PLUMBING-Final 1/23/2023 Approved JAMES CHAVEZ
Service/Power Release 1/23/2023 Approved JAMES CHAVEZ
Service/Power Release 2/1/2023 Approved JAMES CHAVEZ