9969 N STANWIN AVE 91331

Certificate Information: 9969 N STANWIN AVE 91331

Application / Permit
21010-10000-02081
Plan Check / Job No.
B21LA07739
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. NEW DETACHED ADU PER STATE LAW (1-STORY) HYDRANTS AND ACCESS JOINT STAMPING PILOT.
Permit Issued
Issued on 2/24/2022
Issuing Office
Current Status
CofO Issued on 5/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 CARLOS MONTES
Corrections Issued 6/9/2021 CARLOS MONTES
Quality Review Completed 6/15/2021 HERNAN ARREOLA
Applicant returned to address corrections 6/30/2021 CARLOS MONTES
Applicant returned to address corrections 7/13/2021 CARLOS MONTES
Applicant returned to address corrections 8/19/2021 CARLOS MONTES
Plan Check Approved 12/8/2021 CARLOS MONTES
Issued 2/24/2022 APPLICANT
CofO in Progress 5/9/2023 MICHEL ABAJAN
Permit Finaled 5/15/2023 MICHAEL SMITH
CofO Issued 5/15/2023 MICHAEL SMITH
Permit Finaled 5/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/7/2021 KURT CORRAL
Address approval Cleared 12/1/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/1/2021 CARLOS AGUILERA
Sewer availability Cleared 12/2/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/6/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/29/2022 Corrections Issued MICHAEL TEMPLE
METHANE-Barrier 3/29/2022 Not Ready for Inspection MICHAEL TEMPLE
METHANE-Subgrade 3/29/2022 Not Ready for Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 4/8/2022 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 4/8/2022 Not Ready for Inspection MICHEL ABAJAN
METHANE-Subgrade 4/8/2022 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 4/18/2022 Approved MICHEL ABAJAN
METHANE-Barrier 4/18/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 4/18/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/29/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 4/29/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/9/2022 Corrections Issued JOHN HAYES
Green Building Rough 6/9/2022 Not Ready for Inspection JOHN HAYES
METHANE-Rough 6/9/2022 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 6/9/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Corrections Issued MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 6/16/2022 Approved MICHEL ABAJAN
Deputy Wood Construction 6/22/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/24/2022 Approved MICHEL ABAJAN
Green Building Rough 6/24/2022 Approved MICHEL ABAJAN
METHANE-Rough 6/24/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 6/24/2022 Approved MICHEL ABAJAN
Insulation 6/30/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Drywall Nailing 7/6/2022 Partial Approval OGANES TARAKHCHYAN
Insulation 7/6/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/6/2022 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/11/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 2/16/2023 Approved MICHEL ABAJAN
Gas Test 2/16/2023 Approved MICHEL ABAJAN
Final 4/10/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 4/10/2023 Approved MICHEL ABAJAN
HVAC-Final 4/10/2023 Approved MICHEL ABAJAN
PLUMBING-Final 4/10/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 4/10/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 4/10/2023 Approved MICHEL ABAJAN
Final 5/9/2023 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 5/9/2023 Approved MICHEL ABAJAN