2823 S UNIVERSITY AVE 90007

Certificate Information: 2823 S UNIVERSITY AVE 90007

Application / Permit
21010-10000-02076
Plan Check / Job No.
B21LA07707
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU for (E) fraternity house per state law GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)-(d), (g). " The LID clearance has been deferred. Approval of LID requirements shall be obtained from LASAN prior to the finalizing of the permit."
Permit Issued
Issued on 8/25/2022
Issuing Office
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 HELEN NGUYEN
Disabled Access Plans Picked Up 5/14/2021 APPLICANT
Corrections Issued 5/18/2021 HELEN NGUYEN
Quality Review Completed 5/21/2021 MICHAEL PEREZ
Applicant returned to address corrections 7/12/2021 HELEN NGUYEN
Applicant returned to address corrections 8/18/2021 HELEN NGUYEN
Applicant returned to address corrections 10/13/2021 HELEN NGUYEN
Applicant returned to address corrections 11/17/2021 HELEN NGUYEN
Plan Check Approved 1/12/2022 HELEN NGUYEN
No Progress 2/16/2022 HELEN NGUYEN
Plan Check Approved 6/30/2022 MAHNAZ NOURHASHEMI
Issued 8/25/2022 APPLICANT
CofO in Progress 5/7/2024 ALEJANDRO DE ARTOLA
Permit Finaled 5/17/2024 DEROLD HAUFF
CofO Issued 5/17/2024 DEROLD HAUFF
Permit Finaled 5/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Historic Resource Verification Cleared 5/26/2021 MICAELA TORRES-GIL
Address approval Cleared 6/1/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/1/2021 RENZ SORIANO
Sewer availability Cleared 6/1/2021 RENZ SORIANO
DAS Clearance Cleared 6/4/2021 SHINE LIN
Redevelopment Project Area Cleared 6/18/2021 GRACIELA ACOSTA
ZA Case Cleared 6/18/2021 JASON CHAN
ZI Cleared 6/18/2021 JASON CHAN
Green Code Cleared 7/23/2021 HELEN NGUYEN
Highway dedication Cleared 9/10/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 9/12/2021 ROBERT DUFF
Roof/Waste drainage to street Cleared 9/16/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 2/26/2022 JEANETTE VONG
Redevelopment Project Area Cleared 3/3/2022 SUSAN WONG
Sewer availability Cleared 3/3/2022 JEANETTE VONG
DAS Clearance Cleared 3/16/2022 HELEN NGUYEN
Hydrant and Access approval Cleared 5/3/2022 KURT CORRAL

Contact Information

Architect Badie,, Amin; Lic. No.: C28846 4386 BECK AVENUE      STUDIO CITY, CA 91604
Contractor Mid Construction Group; Lic. No.: 1030925-B 5850 W 3RD STREET #160      LOS ANGELES, CA 90036
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Geologist Fujita,, Samantha Jane; Lic. No.: GEO9042 16414 VAN NESS AVE      TORRANCE, CA 90504

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/17/2023 Corrections Issued BRENDAN MORELLI
Deputy Reinf. Concrete 2/22/2023 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 2/23/2023 Partial Approval BRENDAN MORELLI
METHANE-Barrier 2/23/2023 Approved BRENDAN MORELLI
METHANE-Subgrade 2/23/2023 Approved BRENDAN MORELLI
Footing/Foundation/Slab 3/2/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/7/2023 Partial Approval BRENDAN MORELLI
Deputy Reinf. Concrete 3/9/2023 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval BRENDAN MORELLI
Green Building Rough 3/29/2023 Not Ready for Inspection BRENDAN MORELLI
METHANE-Rough 3/29/2023 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 3/29/2023 Not Ready for Inspection BRENDAN MORELLI
Deputy Drilled-In Anchors 4/14/2023 Conditional Approval BRENDAN MORELLI
Deputy Wood Construction 4/14/2023 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/18/2023 Partial Approval BRENDAN MORELLI
Deputy Methane Barrier 5/1/2023 Conditional Approval BRENDAN MORELLI
Green Building Rough 5/11/2023 Not Ready for Inspection BRENDAN MORELLI
Interior/Exterior Lathing 5/11/2023 Partial Approval BRENDAN MORELLI
Verify Sprinkler Sign Off 5/11/2023 Approved BRENDAN MORELLI
Wood Frame 5/11/2023 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 5/19/2023 Approved BRENDAN MORELLI
Wood Frame 5/19/2023 Approved BRENDAN MORELLI
Insulation 5/23/2023 Corrections Issued BRENDAN MORELLI
Drywall Nailing 5/25/2023 Not Ready for Inspection STUART CHAPMAN
Insulation 5/25/2023 Approved STUART CHAPMAN
Drywall Nailing 5/31/2023 Approved BRENDAN MORELLI
Pre-Inspection 5/31/2023 Off-Hour Fees Due
Final 7/7/2023 No Access for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 7/7/2023 Approved BRENDAN MORELLI
Green Building Final 7/7/2023 No Access for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 7/7/2023 No Access for Inspection BRENDAN MORELLI
Final 8/14/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/14/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/14/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/16/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/16/2023 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/16/2023 Approved ALEJANDRO DE ARTOLA
Final 8/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/6/2024 OK to Issue CofO ALEJANDRO DE ARTOLA