538 N CHAUTAUQUA BLVD 90272
Certificate Information: 538 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 21010-10000-02073
- Plan Check / Job No.
- B21LA07688
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 82'X74' 2-STORY SFD 8302 SF WITH BASEMENT AND ATTACHED 1-CAR GARAGE AT BASEMENT AND 2-CAR GARAGE ON 1ST FLOOR. 1 OF 6
- Permit Issued
- Issued on 12/29/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | CHUNG-WEN CHUANG |
| Corrections Issued | 6/3/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 6/10/2021 | JASON HEALEY |
| Applicant returned to address corrections | 11/1/2021 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 11/3/2021 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 11/5/2021 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 11/15/2021 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 12/13/2021 | CHUNG-WEN CHUANG |
| Plan Check Approved | 12/15/2021 | CHUNG-WEN CHUANG |
| Issued | 12/29/2021 | APPLICANT |
| Building Plans Picked Up | 12/30/2021 | APPLICANT |
| CofO in Progress | 6/7/2024 | ARAM AVEDISIAN |
| Permit Finaled | 6/12/2024 | DANIEL ORRANTE |
| CofO Issued | 6/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/15/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/15/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/15/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/15/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/15/2021 | DINAH GARIN |
| Permit | Cleared | 6/15/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | DINAH GARIN |
| Sewer availability | Cleared | 6/16/2021 | DINAH GARIN |
| Trees in Parkway | Cleared | 8/26/2021 | JOHN KIM |
| Trees in Parkway | Cleared | 8/26/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 8/30/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 11/3/2021 | MATTHEW JENKINS |
| Grading Pre-Inspection | Cleared | 11/3/2021 | MATTHEW JENKINS |
| Low Impact Development | Cleared | 12/3/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/6/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alamir,, Reza; Lic. No.: C79605 | 19 GRANADA AVE 2 LONG BEACH, CA 90803 |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 1722 CEDAR STREET APT G ALHAMBRA, CA 91801 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | Kruger,, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/5/2022 | Approved | ANDREW NAVE |
| Underground Mechanical | 4/11/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Other (see comments) | 4/27/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 4/28/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 5/24/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/25/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/1/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 6/2/2022 | Approved | MICHAEL PELHAM |
| Wood Frame | 7/19/2022 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/12/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 10/13/2022 | Corrections Issued | KENNETH NAGLE |
| Deputy Reinf. Concrete | 10/19/2022 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/21/2022 | Corrections Issued | KEVIN SARGSYAN |
| Reinforced Concrete Frame | 10/21/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 10/24/2022 | Conditional Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/27/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 10/28/2022 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Wood Construction | 11/1/2022 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 11/2/2022 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/3/2022 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/10/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/10/2022 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/10/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/10/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/17/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 11/29/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/5/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 12/5/2022 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/13/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/21/2022 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/21/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 12/22/2022 | Conditional Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/29/2022 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 12/29/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/29/2022 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/2/2023 | Partial Approval | MICHAEL PELHAM |
| Insulation | 5/23/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/23/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/25/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Special/Order Compliance | 5/25/2023 | Partial Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 5/30/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 6/1/2023 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 6/1/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 6/14/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 6/14/2023 | Approved | OGANES TARAKHCHYAN |
| Sewer | 8/14/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/18/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/18/2023 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 8/18/2023 | Partial Approval | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 8/18/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/14/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/10/2024 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 4/10/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Not Ready | EVAN COOPER |
| ELECTRICAL-Final | 4/17/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 4/17/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 4/17/2024 | Approved | ARAM AVEDISIAN |
| Gas Test | 4/19/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Gas Test | 4/23/2024 | Approved | ARAM AVEDISIAN |
| Gas Test | 4/24/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 5/15/2024 | Approved | ARAM AVEDISIAN |
| Final | 5/15/2024 | No Access for Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/15/2024 | Approved | ARAM AVEDISIAN |
| Green Building Final | 5/15/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 5/15/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 5/15/2024 | Approved | ARAM AVEDISIAN |
| Final | 5/17/2024 | Corrections Issued | ARAM AVEDISIAN |
| Service/Power Release | 5/17/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 6/7/2024 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 6/7/2024 | Approved | ARAM AVEDISIAN |