13870 W WEIDNER ST 91331

Certificate Information: 13870 W WEIDNER ST 91331

Application / Permit
21010-10000-02072
Plan Check / Job No.
B21LA07686
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY SINGLE FAMILY PER SB9.
Permit Issued
Issued on 6/13/2022
Issuing Office
Current Status
CofO Issued on 9/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 JOE VO
Corrections Issued 5/15/2021 JOE VO
Quality Review Completed 5/21/2021 MICHAEL PEREZ
Applicant returned to address corrections 6/15/2021 JOE VO
Applicant returned to address corrections 10/5/2021 JOE VO
Applicant returned to address corrections 10/19/2021 JOE VO
Applicant returned to address corrections 2/28/2022 JOE VO
Applicant returned to address corrections 3/25/2022 JOE VO
Plan Check Approved 5/28/2022 JOE VO
Issued 6/13/2022 APPLICANT
CofO in Progress 9/7/2022 MICHEL ABAJAN
CofO Issued 9/8/2022 MICHAEL SMITH
Permit Finaled 9/8/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/12/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/10/2021 CARLOS AGUILERA
Sewer availability Cleared 8/10/2021 CARLOS AGUILERA
Low Impact Development Cleared 8/19/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/25/2021 ABDULLAH SADOZAI
Hydrant and Access approval Cleared 10/25/2021 KURT CORRAL
Construction near power lines Cleared 10/30/2021 RIDWAN HARDY
Clean Up Green Up Cleared 11/1/2021 PABLO ESTRADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2022 Approved MICHEL ABAJAN
METHANE-Barrier 6/17/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 6/17/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 6/24/2022 Partial Approval MICHEL ABAJAN
Wood Frame 6/24/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/13/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/13/2022 Approved MICHEL ABAJAN
Green Building Rough 7/13/2022 Approved MICHEL ABAJAN
HVAC-Rough 7/13/2022 Approved MICHEL ABAJAN
METHANE-Rough 7/13/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 7/13/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 7/13/2022 Approved MICHEL ABAJAN
Insulation 7/15/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/15/2022 Approved MICHEL ABAJAN
Drywall Nailing 7/18/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/25/2022 Approved MICHEL ABAJAN
Final 8/25/2022 Corrections Issued MICHEL ABAJAN
HVAC-Final 8/25/2022 Approved MICHEL ABAJAN
PLUMBING-Final 8/25/2022 Approved MICHEL ABAJAN
Final 8/31/2022 OK to Issue CofO MICHEL ABAJAN
Green Building Final 8/31/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved MICHEL ABAJAN
Service/Power Release 8/31/2022 Approved MICHEL ABAJAN
Smoke Detectors 8/31/2022 Approved MICHEL ABAJAN