11110 N ETIWANDA AVE 91326

Certificate Information: 11110 N ETIWANDA AVE 91326

Application / Permit
21010-10000-02069
Plan Check / Job No.
B21LA07684
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan new ADU. New Detached ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 9/25/2022
Issuing Office
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 CRYSTEL MAALOUF
Corrections Issued 6/9/2021 CRYSTEL MAALOUF
Quality Review Completed 6/15/2021 HERNAN ARREOLA
Applicant returned to address corrections 7/26/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 11/18/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 12/9/2021 CRYSTEL MAALOUF
Plan Check Approved 9/14/2022 CRYSTEL MAALOUF
Issued 9/25/2022 APPLICANT
CofO in Progress 11/30/2023 DAVID SCANTLIN
CofO in Progress 2/14/2024 DAVID SCANTLIN
CofO in Progress 5/17/2024 DAVID SCANTLIN
Permit Finaled 5/17/2024 JOHN JANSON
CofO Issued 5/17/2024 JOHN JANSON
Permit Finaled 5/17/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/23/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/28/2021 CARLOS AGUILERA
Sewer availability Cleared 6/28/2021 CARLOS AGUILERA
Low Impact Development Cleared 11/16/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 11/20/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 12/17/2021 MATTHEW CRAIG
Grading Pre-Inspection Cleared 9/14/2022 HERNAN ARREOLA

Contact Information

Contractor Golden Giant Construction Inc; Lic. No.: 890120-B       ,
Engineer Zhuang,, Wenbin; Lic. No.: NA5236       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 10/27/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 11/2/2022 Conditional Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 12/14/2022 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 12/14/2022 Approved JOHN KIDWELL
Green Building Rough 12/14/2022 Partial Approval JOHN KIDWELL
HVAC-Rough 12/14/2022 Approved JOHN KIDWELL
PLUMBING-Rough 12/14/2022 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/14/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/13/2023 Approved JOHN KIDWELL
Green Building Rough 1/13/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/13/2023 Partial Approval JOHN KIDWELL
Insulation 2/2/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 2/2/2023 Not Ready for Inspection MORRIS JACKSON
Drywall Nailing 2/15/2023 Approved MORRIS JACKSON
Underground Mechanical 7/11/2023 Approved DAVID SCANTLIN
Sewer 7/27/2023 Approved JUSTIN HAWLEY
Final 10/20/2023 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 10/20/2023 Approved DAVID SCANTLIN
Green Building Final 10/20/2023 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved DAVID SCANTLIN
Service/Power Release 10/20/2023 Approved DAVID SCANTLIN
Smoke Detectors 10/20/2023 Approved DAVID SCANTLIN
Final 11/27/2023 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 11/27/2023 Approved DAVID SCANTLIN
Final 11/30/2023 Not Ready for Inspection DAVID SCANTLIN
Special/Order Compliance 12/5/2023 Corrections Issued DAVID SCANTLIN
Final 5/16/2024 OK to Issue CofO DAVID SCANTLIN