2328 S WALNUT AVE 90291
Certificate Information: 2328 S WALNUT AVE 90291
- Application / Permit
- 21010-10000-02062
- Plan Check / Job No.
- B21LA07674
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU conversion.EXISTING GARAGE TO BE CONVERTED TO ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 7/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 4/27/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 7/26/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/17/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/2/2021 | CRYSTEL MAALOUF |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 7/14/2022 | DAVID FEILER |
| No Progress | 7/16/2022 | RICHARD STEINBACH |
| CofO in Progress | 7/18/2022 | RICHARD STEINBACH |
| Permit Finaled | 7/18/2022 | DANIEL ORRANTE |
| CofO Issued | 7/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 7/21/2021 | DENNIS BRAGIN |
| Specific Plan | Cleared | 8/25/2021 | PETE EYRE |
Contact Information
| Contractor | Seacrest Development Inc ; Lic. No.: 1036456-B | 1601 N SEPULVEDA BLVD SUITE 702 MANHATTAN BEACH, CA 90266 |
| Engineer | Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 3/24/2022 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/5/2022 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/7/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 4/7/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 4/7/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 4/20/2022 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 4/20/2022 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 4/26/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 4/26/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 5/6/2022 | Approved | DAVID FEILER |
| Green Building Rough | 5/6/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 5/6/2022 | Corrections Issued | DAVID FEILER |
| Insulation | 5/6/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 5/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 5/16/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/25/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 5/25/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 5/26/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/5/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 7/5/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 7/5/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 7/8/2022 | Corrections Issued | DAVID FEILER |
| Final | 7/8/2022 | Corrections Issued | DAVID FEILER |
| Green Building Final | 7/8/2022 | Approved | DAVID FEILER |
| HVAC-Final | 7/8/2022 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 7/8/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 7/12/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Final | 7/12/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Final | 7/12/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 7/14/2022 | OK to Issue CofO | DAVID FEILER |