10621 S BROADWAY 90003
Certificate Information: 10621 S BROADWAY 90003
- Application / Permit
- 21010-10000-02061
- Plan Check / Job No.
- B21LA07672
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 11/30/2021
- Issuing Office
- Current Status
- CofO Issued on 2/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | DANIEL YIP |
| Corrections Issued | 5/11/2021 | DANIEL YIP |
| Quality Review Completed | 5/19/2021 | JASON HEALEY |
| Applicant returned to address corrections | 9/30/2021 | DANIEL YIP |
| Applicant returned to address corrections | 10/14/2021 | DANIEL YIP |
| Plan Check Approved | 11/16/2021 | DANIEL YIP |
| Issued | 11/30/2021 | APPLICANT |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| CofO in Progress | 2/17/2023 | JAMES CHAVEZ |
| CofO Issued | 2/22/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/22/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2021 | STEVE MELGAR |
| Address approval | Cleared | 6/10/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 6/14/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 7/26/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/31/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/7/2021 | STEVE MELGAR |
| Frnt yard landscape/Water mgmt | Cleared | 11/2/2021 | DANIEL CORONADO |
Contact Information
| Contractor | F S Z Bros General Contractors Inc; Lic. No.: 794097-B | 9036 IMPERIAL HWY DOWNEY, CA 90242 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/27/2022 | Conditional Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/3/2022 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Rec and Parks Fee Memo | 5/9/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 6/14/2022 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Corrections Issued | JOHN KLARIN |
| HVAC-Rough | 6/14/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 6/14/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/15/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 6/15/2022 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Rough | 6/15/2022 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 6/15/2022 | Not Ready for Inspection | JOHN KLARIN |
| Wood Frame | 6/22/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 7/11/2022 | Approved | JOHN KLARIN |
| Insulation | 7/11/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 7/11/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 7/18/2022 | Not Ready for Inspection | JOHN KLARIN |
| Drywall Nailing | 7/20/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/21/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 10/21/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 10/21/2022 | Corrections Issued | JOHN KLARIN |
| MERV13>=Final | 10/21/2022 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Rough | 10/21/2022 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2022 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 10/21/2022 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 10/21/2022 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 10/21/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 12/20/2022 | Approved | JAMES CHAVEZ |
| Gas Test | 12/20/2022 | Approved | JAMES CHAVEZ |
| HVAC-Final | 12/20/2022 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 12/20/2022 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 1/23/2023 | Partial Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 1/23/2023 | Approved | JAMES CHAVEZ |
| Final | 1/23/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Final | 1/23/2023 | Approved | JAMES CHAVEZ |
| HVAC-Final | 1/23/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Final | 1/23/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 1/23/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 1/23/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 1/23/2023 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 1/23/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 1/23/2023 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 1/23/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | JAMES CHAVEZ |
| Final | 2/8/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Service/Power Release | 2/8/2023 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 2/8/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 2/15/2023 | Approved | JAMES CHAVEZ |