1448 W 219TH ST 90501
Certificate Information: 1448 W 219TH ST 90501
- Application / Permit
- 21010-10000-02039
- Plan Check / Job No.
- B21LA07579
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1,200 SF SFD DETACHED ADU PER LAMC 12.22 A.33(c) AND (d) LOCATED ON A LOT WITH AN EXISTING PRIMARY RESIDENCE ALL CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 5/4/2022
- Issuing Office
- Current Status
- CofO Issued on 3/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | DANIEL SANJUAN |
| Corrections Issued | 6/3/2021 | DANIEL SANJUAN |
| Quality Review Completed | 6/8/2021 | HANS SANTIAGO |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| Applicant returned to address corrections | 1/20/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 4/1/2022 | VIVIAN LAO |
| Plan Check Approved | 5/4/2022 | VIVIAN LAO |
| Issued | 5/4/2022 | APPLICANT |
| CofO in Progress | 1/20/2023 | EUGENE CASSIDY |
| CofO Issued | 3/6/2023 | ANSON MAGLASANG |
| Permit Finaled | 3/6/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 8/18/2021 | CHINH DINH |
| Hydrant and Access approval | Cleared | 9/10/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/9/2021 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 12/13/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/8/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 7/8/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/11/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/29/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/29/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 7/29/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 7/29/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/29/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/2/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/3/2022 | Approved | EUGENE CASSIDY |
| Green Building Rough | 8/3/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 8/3/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/3/2022 | Approved | EUGENE CASSIDY |
| Insulation | 8/8/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/11/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/11/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 9/19/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 9/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 9/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 9/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 9/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Rec and Parks Fee Memo | 9/19/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/26/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 9/26/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/26/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 9/26/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 9/26/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 9/26/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 9/26/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/2/2022 | Partial Approval | JOHN KLARIN |
| Final | 12/2/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/2/2022 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 12/2/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 1/12/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/12/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 1/12/2023 | Not Required | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/20/2023 | Approved | EUGENE CASSIDY |
| Final | 1/20/2023 | OK to Issue CofO | EUGENE CASSIDY |