1448 W 219TH ST 90501

Certificate Information: 1448 W 219TH ST 90501

Application / Permit
21010-10000-02039
Plan Check / Job No.
B21LA07579
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1,200 SF SFD DETACHED ADU PER LAMC 12.22 A.33(c) AND (d) LOCATED ON A LOT WITH AN EXISTING PRIMARY RESIDENCE ALL CONSTRUCTION PER WFPP.
Permit Issued
Issued on 5/4/2022
Issuing Office
Current Status
CofO Issued on 3/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 DANIEL SANJUAN
Corrections Issued 6/3/2021 DANIEL SANJUAN
Quality Review Completed 6/8/2021 HANS SANTIAGO
Building Plans Picked Up 6/11/2021 APPLICANT
Applicant returned to address corrections 1/20/2022 DANIEL SANJUAN
Applicant returned to address corrections 4/1/2022 VIVIAN LAO
Plan Check Approved 5/4/2022 VIVIAN LAO
Issued 5/4/2022 APPLICANT
CofO in Progress 1/20/2023 EUGENE CASSIDY
CofO Issued 3/6/2023 ANSON MAGLASANG
Permit Finaled 3/6/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/14/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 7/14/2021 ERIK BEASLEY
Sewer availability Cleared 8/18/2021 CHINH DINH
Hydrant and Access approval Cleared 9/10/2021 MATTHEW CRAIG
Low Impact Development Cleared 12/9/2021 JULIAN SUNG
Roof/Waste drainage to street Cleared 12/13/2021 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/1/2022 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 7/8/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 7/8/2022 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 7/11/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 7/29/2022 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 7/29/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 7/29/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 7/29/2022 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 7/29/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 8/2/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/3/2022 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/3/2022 Approved EUGENE CASSIDY
Green Building Rough 8/3/2022 Approved EUGENE CASSIDY
HVAC-Rough 8/3/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/3/2022 Approved EUGENE CASSIDY
Insulation 8/8/2022 Approved EUGENE CASSIDY
Drywall Nailing 8/11/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/11/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 9/19/2022 Not Ready for Inspection EUGENE CASSIDY
Final 9/19/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 9/19/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 9/19/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 9/19/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 9/19/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 9/19/2022 Not Ready for Inspection EUGENE CASSIDY
Verify Rec and Parks Fee Memo 9/19/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 9/26/2022 Not Ready for Inspection EUGENE CASSIDY
Final 9/26/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 9/26/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 9/26/2022 Approved EUGENE CASSIDY
PLUMBING-Final 9/26/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 9/26/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 9/26/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 12/2/2022 Partial Approval JOHN KLARIN
Final 12/2/2022 Corrections Issued JOHN KLARIN
Green Building Final 12/2/2022 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 12/2/2022 Not Ready for Inspection JOHN KLARIN
Final 1/12/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 1/12/2023 Approved EUGENE CASSIDY
Service/Power Release 1/12/2023 Not Required EUGENE CASSIDY
ELECTRICAL-Final 1/20/2023 Approved EUGENE CASSIDY
Final 1/20/2023 OK to Issue CofO EUGENE CASSIDY