1635 W ENTERPRISE DR 90732

Certificate Information: 1635 W ENTERPRISE DR 90732

Application / Permit
21010-10000-01969
Plan Check / Job No.
B21LA07470
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 41'X21' 3-STORY DETACHED SFD 1743 SF W/ ATTACHED 2-CAR GARAGE 443 SF. PLAN TYPE 2C.
Permit Issued
Issued on 3/9/2022
Issuing Office
Current Status
CofO Issued on 3/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 CHUNG-WEN CHUANG
Plans on Hold 8/5/2021 JASON HEALEY
Hold Released 8/11/2021 ALLEN MANALANSAN
Corrections Issued 8/23/2021 CHUNG-WEN CHUANG
Quality Review Completed 8/25/2021 JASON HEALEY
Applicant returned to address corrections 9/8/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 9/21/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 9/30/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 10/4/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 10/26/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 11/17/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 12/7/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 12/9/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 12/17/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 12/21/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 1/12/2022 CHUNG-WEN CHUANG
Applicant returned to address corrections 1/26/2022 CHUNG-WEN CHUANG
Applicant returned to address corrections 2/7/2022 CHUNG-WEN CHUANG
Applicant returned to address corrections 2/15/2022 CHUNG-WEN CHUANG
Plan Check Approved 2/23/2022 CHUNG-WEN CHUANG
Issued 3/9/2022 APPLICANT
Building Plans Picked Up 3/10/2022 APPLICANT
CofO in Progress 12/18/2024 JOSEPH MCGARRY
Permit Finaled 3/7/2025 ANSON MAGLASANG
CofO Issued 3/7/2025 ANSON MAGLASANG
Permit Finaled 3/7/2025 ANSON MAGLASANG

Permit Application Clearance Information

CPC Cleared 10/25/2021 JASON CHAN
CPC Cleared 10/25/2021 JASON CHAN
CPC Cleared 10/25/2021 JASON CHAN
Frnt yard landscape/Water mgmt Cleared 10/25/2021 JASON CHAN
Miscellaneous Cleared 10/25/2021 JASON CHAN
Miscellaneous Cleared 10/25/2021 JASON CHAN
Miscellaneous Cleared 10/25/2021 JASON CHAN
Miscellaneous Cleared 10/25/2021 JASON CHAN
Miscellaneous Cleared 10/25/2021 JASON CHAN
Miscellaneous Cleared 10/25/2021 JASON CHAN
Miscellaneous Cleared 10/25/2021 JASON CHAN
Opn space landscape/Water mgmt Cleared 10/25/2021 JASON CHAN
Private street Cleared 10/25/2021 JASON CHAN
Prkng lot landscape/Water mgmt Cleared 10/25/2021 JASON CHAN
Specific Plan Cleared 10/25/2021 JASON CHAN
ZA Case Cleared 10/25/2021 JASON CHAN
DAS Clearance Cleared 11/17/2021 CHUNG-WEN CHUANG
Building over 36-ft Cleared 12/17/2021 CALOSHA APPROVED
Low Impact Development Cleared 12/20/2021 AMMAR ELTAWIL
Trees in Parkway Cleared 12/21/2021 CHUNG-WEN CHUANG
Miscellaneous Cleared 1/7/2022 JASON CHAN
Address approval Cleared 1/21/2022 DINAH GARIN
Drainage to Storm Drain Cleared 1/21/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/21/2022 DINAH GARIN
Highway dedication Cleared 1/21/2022 DINAH GARIN
Permit Cleared 1/21/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 1/21/2022 DINAH GARIN
Sewer availability Cleared 1/21/2022 DINAH GARIN
Hydrant and Access approval Cleared 1/25/2022 JOHN CONNEALLY
Grading Pre-Inspection Cleared 1/26/2022 VASIL MIHALEV
Construction near power lines Cleared 2/3/2022 WALTER RAMIREZ
Construction within easement Cleared 2/3/2022 WALTER RAMIREZ
GPI Written Notices Cleared 2/17/2022 CHUNG-WEN CHUANG

Contact Information

Architect Laullon,, Fernando; Lic. No.: C27224 WILLIAM HEZMALHALCH ARCHITECTS   2850 REDHILL AVE STE 200    SANTA ANA, CA 92705
Contractor Owner-Builder       ,
Engineer Christian,, Dale Alan; Lic. No.: S2705 1744 W KATELLA AVENUE SUITE 107      ORANGE, CA 92867
Engineer Douglas,, Ryan Lewis; Lic. No.: GE3147 45 VIA VILLENA      SAN CLEMENTE, CA 92673
Engineer Waddell,, Ian R; Lic. No.: C41219 519 10TH ST      HUNTINGTON BEACH, CA 92648
Engineer Zhao,, Xiaoming; Lic. No.: C70068 13402 PARK DR      CERRITOS, CA 90703
Geologist Graham,, Barry Paul; Lic. No.: EG2749 14762 BRIDGEPORT ROAD      TUSTIN, CA 92780

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/15/2022 Partial Approval ANSON MAGLASANG
Underground Mechanical 3/16/2022 Partial Inspection ANSON MAGLASANG
Footing/Foundation/Slab 3/23/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Partial Approval ANSON MAGLASANG
Wood Frame 4/20/2022 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Partial Approval ANSON MAGLASANG
Wood Frame 5/10/2022 Partial Approval ANSON MAGLASANG
ELECTRICAL-Rough 6/7/2022 Approved ANSON MAGLASANG
HVAC-Rough 6/7/2022 Approved ANSON MAGLASANG
PLUMBING-Rough 6/7/2022 Approved ANSON MAGLASANG
Insulation 6/13/2022 Approved ANSON MAGLASANG
Drywall Nailing 6/21/2022 Approved ANSON MAGLASANG
Green Building Rough 6/21/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 6/21/2022 Partial Approval ANSON MAGLASANG
Interior/Exterior Lathing 6/24/2022 Partial Approval ANSON MAGLASANG
Gas Test 7/13/2022 Approved ANSON MAGLASANG
Service/Power Release 8/10/2022 Corrections Issued ANSON MAGLASANG
Service/Power Release 8/17/2022 Not Ready for Inspection ANSON MAGLASANG
Service/Power Release 9/12/2022 Not Ready for Inspection ANSON MAGLASANG
Service/Power Release 9/22/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 12/11/2024 Approved JOSEPH MCGARRY
Final 12/11/2024 Corrections Issued JOSEPH MCGARRY
Green Building Final 12/11/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/11/2024 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 12/11/2024 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 12/11/2024 Approved JOSEPH MCGARRY
Final 12/17/2024 OK to Issue CofO JOSEPH MCGARRY