3868 S CLOVERDALE AVE 90008
Certificate Information: 3868 S CLOVERDALE AVE 90008
- Application / Permit
- 21010-10000-01966
- Plan Check / Job No.
- B21LA07451
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) & (d). HYDRANTS AND ACCESS JOINT STAMPING PILOT.
- Permit Issued
- Issued on 2/1/2022
- Issuing Office
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | LAMAR DAVIS |
| Corrections Issued | 6/1/2021 | LAMAR DAVIS |
| Quality Review Completed | 6/9/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/14/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 8/10/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 9/7/2021 | LAMAR DAVIS |
| Building Plans Picked Up | 11/17/2021 | APPLICANT |
| Plan Check Approved | 1/20/2022 | LAMAR DAVIS |
| Issued | 2/1/2022 | APPLICANT |
| CofO in Progress | 10/19/2023 | ANTHONY EGSON |
| Permit Finaled | 10/23/2023 | DEROLD HAUFF |
| CofO Issued | 10/23/2023 | DEROLD HAUFF |
| Permit Finaled | 10/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/30/2021 | BRIAN MILLER |
| Address approval | Cleared | 6/16/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 6/16/2021 | RENZ SORIANO |
| Miscellaneous | Cleared | 9/7/2021 | CASEY JENSEN |
| Low Impact Development | Cleared | 9/8/2021 | MARCO SANCHEZ |
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 9/16/2021 | ALEXANDER HELFER |
| Roof/Waste drainage to street | Cleared | 9/17/2021 | CELINA MORENO |
| Miscellaneous | Cleared | 11/15/2021 | LAMAR DAVIS |
| Hydrant and Access approval | Cleared | 12/9/2021 | MATTHEW CRAIG |
Contact Information
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/25/2022 | Corrections Issued | ANTHONY EGSON |
| Sewer | 2/25/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 2/25/2022 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 3/4/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/4/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 3/25/2022 | Approved | ANTHONY EGSON |
| Insulation | 3/29/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Approved | ANTHONY EGSON |
| Deck | 5/13/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/13/2022 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/13/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/20/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/20/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 5/20/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/20/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 5/20/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/13/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/13/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 6/13/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 6/13/2022 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 6/13/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/17/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 6/17/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/17/2022 | Approved | ANTHONY EGSON |
| Insulation | 6/22/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 7/8/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/15/2022 | No Access for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/20/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2022 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/6/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/6/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/14/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 12/14/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/2/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 2/9/2023 | No Access for Inspection | STUART CHAPMAN |
| Final | 3/6/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/6/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 3/6/2023 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 3/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 3/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 3/13/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 3/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 3/13/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 3/28/2023 | Approved | ANTHONY EGSON |
| Gas Test | 3/28/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 3/28/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/28/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 4/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 4/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 4/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 4/3/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 8/29/2023 | Approved | ANTHONY EGSON |
| Final | 10/3/2023 | Partial Approval | ANTHONY EGSON |
| Green Building Final | 10/3/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 10/3/2023 | Approved | ANTHONY EGSON |
| Final | 10/19/2023 | OK to Issue CofO | ANTHONY EGSON |