537-537 1/2 W 93RD ST 90044

Certificate Information: 537-537 1/2 W 93RD ST 90044

Application / Permit
21010-10000-01951
Plan Check / Job No.
B21LA07365
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW (39.5' X 35') 2-STORY DUPLEX WITH ATTACHED GARAGE (FRONT BLDG) 1 OF 2
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 9/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 VIVIAN LAO
Corrections Issued 5/13/2021 VIVIAN LAO
Quality Review Completed 5/20/2021 MICHAEL PEREZ
Building Plans Picked Up 5/21/2021 APPLICANT
Applicant returned to address corrections 9/8/2021 VIVIAN LAO
Plan Check Approved 9/28/2021 VIVIAN LAO
Issued 12/2/2021 APPLICANT
CofO in Progress 9/7/2022 ANSON MAGLASANG
Permit Finaled 9/11/2022 DEROLD HAUFF
CofO Issued 9/11/2022 DEROLD HAUFF
Permit Finaled 9/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/3/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/8/2021 WALLIE JONG
Hydrant and Access approval Cleared 7/21/2021 MATTHEW CRAIG
Sewer availability Cleared 7/21/2021 WALLIE JONG
Low Impact Development Cleared 8/27/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/27/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/14/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 1/26/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Partial Approval ALIZAH MAYAGOITIA
Insulation 1/27/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 4/4/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 4/4/2022 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 4/4/2022 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 4/4/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/11/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/11/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 4/11/2022 Approved ALEJANDRO DE ARTOLA
Insulation 4/11/2022 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 4/11/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/5/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/5/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/26/2022 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 5/26/2022 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/12/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 7/14/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 8/12/2022 Approved JOHN KLARIN
ELECTRICAL-Final 8/12/2022 Approved JOHN KLARIN
Final 8/12/2022 Corrections Issued JOHN KLARIN
Green Building Final 8/12/2022 Approved JOHN KLARIN
HVAC-Final 8/12/2022 Approved JOHN KLARIN
PLUMBING-Final 8/12/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/12/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 8/12/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 8/12/2022 Approved JOHN KLARIN
Final 8/25/2022 OK to Issue CofO JOHN KLARIN
Service/Power Release 8/25/2022 Approved JOHN KLARIN
Service/Power Release 9/7/2022 Approved ANSON MAGLASANG