1816 W 24TH ST 90018

Certificate Information: 1816 W 24TH ST 90018

Application / Permit
21010-10000-01945
Plan Check / Job No.
B21LA07354
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SINGLE FAMILY DWELLING IN THE FRONT
Permit Issued
Issued on 9/9/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 DANIEL YIP
Corrections Issued 5/13/2021 DANIEL YIP
Quality Review Completed 5/18/2021 JASON HEALEY
Building Plans Picked Up 5/25/2021 APPLICANT
Plan Check Approved 8/27/2021 DANIEL YIP
Issued 9/9/2021 APPLICANT
CofO in Progress 5/10/2022 KATHRYN BUTTERWORTH
Permit Finaled 5/21/2022 DEROLD HAUFF
CofO Issued 5/21/2022 DEROLD HAUFF
Permit Finaled 5/21/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/9/2021 WALLIE JONG
Community Plan Implem. Overlay Cleared 6/9/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/10/2021 WALLIE JONG
Sewer availability Cleared 6/10/2021 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 6/24/2021 RUBEN VASQUEZ
Community Plan Implem. Overlay Cleared 7/19/2021 RAFAEL FONTES
Hydrant and Access approval Cleared 7/23/2021 MATTHEW CRAIG
Low Impact Development Cleared 8/17/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/18/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/15/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 9/15/2021 Partial Approval KATHRYN BUTTERWORTH
METHANE-Rough 9/17/2021 Partial Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 9/29/2021 Approved SCOTT FINNILA
Footing/Foundation/Slab 9/29/2021 Partial Approval SCOTT FINNILA
METHANE-Barrier 9/29/2021 Approved SCOTT FINNILA
METHANE-Subgrade 9/29/2021 Approved SCOTT FINNILA
Pre-Inspection 9/29/2021 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Approved STUART CHAPMAN
Special/Order Compliance 10/15/2021 Approved HECTOR ALIKHAN
Special/Order Compliance 10/15/2021 Corrections Issued HECTOR ALIKHAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 12/28/2021 Approved KATHRYN BUTTERWORTH
METHANE-Rough 12/28/2021 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 12/28/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 1/5/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/5/2022 Approved ALEJANDRO DE ARTOLA
Gas Test 1/5/2022 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 1/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 1/5/2022 Approved ALEJANDRO DE ARTOLA
METHANE-Rough 1/5/2022 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 1/5/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/11/2022 Approved ALEJANDRO DE ARTOLA
Green Building Rough 1/11/2022 Approved ALEJANDRO DE ARTOLA
Insulation 1/11/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 1/25/2022 Partial Approval KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/25/2022 Approved KATHRYN BUTTERWORTH
Drywall Nailing 1/31/2022 Approved KATHRYN BUTTERWORTH
Sewer 3/3/2022 Approved KATHRYN BUTTERWORTH
Underground Mechanical 3/3/2022 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 3/24/2022 Corrections Issued KATHRYN BUTTERWORTH
Gas Test 3/24/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 3/24/2022 Corrections Issued KATHRYN BUTTERWORTH
Gas Test 3/31/2022 Approved KATHRYN BUTTERWORTH
HVAC-Final 3/31/2022 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 3/31/2022 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 5/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 5/2/2022 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/2/2022 Approved KATHRYN BUTTERWORTH
Green Building Final 5/2/2022 Approved KATHRYN BUTTERWORTH
MERV13>=Final 5/2/2022 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 5/2/2022 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 5/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 5/2/2022 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 5/4/2022 Approved KATHRYN BUTTERWORTH
Final 5/4/2022 OK to Issue CofO KATHRYN BUTTERWORTH
Service/Power Release 5/4/2022 Approved KATHRYN BUTTERWORTH