2941 1/2 S RIMPAU BLVD 90016
Certificate Information: 2941 1/2 S RIMPAU BLVD 90016
- Application / Permit
- 21010-10000-01936
- Plan Check / Job No.
- B21LA07306
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- e-plan: PROPOSED ADDITION TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 11/19/2021
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | MICHAEL LOPEZ |
| Corrections Issued | 6/4/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 6/9/2021 | HERNAN ARREOLA |
| Plan Check Approved | 11/10/2021 | MICHAEL LOPEZ |
| Issued | 11/19/2021 | APPLICANT |
| CofO in Progress | 12/19/2022 | STUART CHAPMAN |
| Permit Finaled | 12/24/2022 | DEROLD HAUFF |
| CofO Issued | 12/24/2022 | DEROLD HAUFF |
| Permit Finaled | 12/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 7/29/2021 | STEVE MELGAR |
| CPC | Cleared | 8/20/2021 | JOE LUCKEY |
| Tenant Habitability Plan | Cleared | 9/1/2021 | MICHAEL SOTO |
| Hydrant and Access approval | Cleared | 9/17/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 10/8/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 10/25/2021 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/7/2021 | Approved | STUART CHAPMAN |
| Pre-Inspection | 12/15/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/23/2021 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 1/4/2022 | Partial Approval | STUART CHAPMAN |
| Pre-Inspection | 1/4/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 2/1/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/1/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 4/4/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Wood Construction | 4/6/2022 | Conditional Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/21/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/21/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 4/21/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/21/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 4/26/2022 | Partial Approval | JOSE AVILA |
| Insulation | 5/10/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/10/2022 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 6/13/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/16/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 7/28/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/2/2022 | Approved | STUART CHAPMAN |
| Final | 8/2/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/2/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/2/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 8/2/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/19/2022 | Approved | STUART CHAPMAN |
| Final | 8/19/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 8/19/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/19/2022 | Approved | STUART CHAPMAN |
| Final | 12/16/2022 | OK to Issue CofO | STUART CHAPMAN |