2941 1/2 S RIMPAU BLVD 90016

Certificate Information: 2941 1/2 S RIMPAU BLVD 90016

Application / Permit
21010-10000-01936
Plan Check / Job No.
B21LA07306
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
e-plan: PROPOSED ADDITION TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 11/19/2021
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 MICHAEL LOPEZ
Corrections Issued 6/4/2021 MICHAEL LOPEZ
Quality Review Completed 6/9/2021 HERNAN ARREOLA
Plan Check Approved 11/10/2021 MICHAEL LOPEZ
Issued 11/19/2021 APPLICANT
CofO in Progress 12/19/2022 STUART CHAPMAN
Permit Finaled 12/24/2022 DEROLD HAUFF
CofO Issued 12/24/2022 DEROLD HAUFF
Permit Finaled 12/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/29/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/29/2021 STEVE MELGAR
Sewer availability Cleared 7/29/2021 STEVE MELGAR
CPC Cleared 8/20/2021 JOE LUCKEY
Tenant Habitability Plan Cleared 9/1/2021 MICHAEL SOTO
Hydrant and Access approval Cleared 9/17/2021 ROBERT DUFF
Low Impact Development Cleared 10/8/2021 KHAING AYE
Roof/Waste drainage to street Cleared 10/25/2021 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/7/2021 Approved STUART CHAPMAN
Pre-Inspection 12/15/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 12/23/2021 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 1/4/2022 Partial Approval STUART CHAPMAN
Pre-Inspection 1/4/2022 Approved STUART CHAPMAN
PLUMBING-Rough 2/1/2022 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 3/1/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Partial Approval STUART CHAPMAN
Green Building Rough 4/4/2022 Not Ready for Inspection STUART CHAPMAN
Deputy Wood Construction 4/6/2022 Conditional Approval STUART CHAPMAN
ELECTRICAL-Rough 4/20/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 4/21/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 4/21/2022 Approved STUART CHAPMAN
HVAC-Rough 4/21/2022 Approved STUART CHAPMAN
PLUMBING-Rough 4/21/2022 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 4/26/2022 Partial Approval JOSE AVILA
Insulation 5/10/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/10/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 6/13/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/16/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 7/28/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 8/2/2022 Approved STUART CHAPMAN
Final 8/2/2022 Corrections Issued STUART CHAPMAN
Green Building Final 8/2/2022 Approved STUART CHAPMAN
Green Building Rough 8/2/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 8/2/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 8/19/2022 Approved STUART CHAPMAN
Final 8/19/2022 Corrections Issued STUART CHAPMAN
HVAC-Final 8/19/2022 Approved STUART CHAPMAN
PLUMBING-Final 8/19/2022 Approved STUART CHAPMAN
Final 12/16/2022 OK to Issue CofO STUART CHAPMAN